S
PECIAL SQUAD TO SURVEY SALEM’’S SAGAThe Nuclear Regulatory Commission (NRC) announced on October 21, 2008, that it was
dispatching a special inspection team to look into “
an apparent loss of reactor coolant systeminventory control
” involving the Unit 1 reactor at the Salem Generating Station in southwesternNew Jersey the prior week. Operators had shut down the unit for refueling and were removing
water from the reactor’s cooling system to allow inspections and maintenance of equipment.
They did not realize that the instrumentation used to monitor the water level had malfunctioned
with the actual water level much lower than the level shown on the faulty instruments. Luckily,
the problem was discovered before it led to inadequate reactor core cooling and resulting fuel
damage. The operators added water back to the cooling system to restore the level to the proper
range.
Salem Unit 1 has a pressurized water reactor (PWR). When the unit is operating, the heat
generated by fissioning atoms in the reactor core warms water in the primary loop to nearly
550°F. Because this water is maintained at high pressure (about 2,200 pounds per square inch,
nearly 100 time the pressure of a car’s tire), it does not boil. Instead, this hot water flows inside
U-shaped tubes within the steam generator. Heat passes through the thin metal tube walls to boil
lower pressure water outside the tubes. The steam moves through the turbine, which is connected
to the generator producing the electricity that is the unit’s
raison de etre. During reactoroperation, the pressurizer is partially filled with water. As implied by its name, the pressurizer
controls pressure. Electric coils in the bottom of the pressurizer can be turned on to raise the
pressure of the primary loop water. Sprays of cold water into the pressurizer’s upper region can
be turned on to lower the pressure.
October 22, 2008
Page 2 of 3
When the unit is shut down for refueling, water is drained from the pressurizer. Part of the
refueling outage steps include lowering the water level in the primary loop to what is termed
“mid-loop,” which is roughly when the piping from the reactor vessel’s nozzles partially empties
of water. This step is risky. Figure 2 is from NRC Information Notice 2000-13.
* The horizontalaxis shows the day during a typical refueling outage. The vertical axis shows the risk of reactor
meltdown; lowest at the bottom and increasing towards the top. The two highest risk points
during refueling occur on days 6 and 20 when the primary loop (also called the reactor coolant
system or RCS) is drained to mid-loop. This NRC information notice also states that the risk
from 22 hours of mid-loop operation approximately equals the risk from operating the reactor at
full power for 33 days.
Why is the risk of reactor meltdown so high when the unit is shut down? Although the nuclear
chain reaction is terminated when the unit shuts down, the radioactive decay of fission
byproducts continues to generate large amounts of heat. In fact, right after the unit is shut down
and all control rods are inserted to stop the nuclear chain reaction, the heat from radioactive
decay equals nearly seven percent of the heat produced by the reactor operating at full power.
Two factors combine to make the mid-loop risk so high. First, the inventory of water in the
primary loop is intentionally lowered to its minimum amount. As a result, if something were to
happen, the margin to draining or boiling away this inventory and causing reactor core
overheating is very small. In addition, federal regulations require many safety systems to be
available when the reactor is operating. Should something happen, all of these safety system
must fail to cause a reactor meltdown. During mid-loop operation, the majority of safety systems
are disabled for testing, inspections, and maintenance. If something were to happen, it takes very
little else going wrong for reactor meltdown to occur.
*
Available online at http://www.nrc.October 22, 2008
Page 3 of 3
Salem’s saga is not the first water level instrumentation problem during refueling. For example:
•
Beaver Valley Unit 1 (PA): On March 26, 1981, leakage from tygon tubing used fortemporary water level monitoring instrumentation caused the indicated level to be
significantly higher than the actual level. As a result, the water level dropped low enough
to interrupt the flow through the reactor’s cooling system. In the hour it took the
operators to re-fill the system and restart the cooling system, the water temperature
heated up over 66°F.
•
Vogtle Unit 1 (GA): On October 26, 1991, the water level monitoring instrumentationcaused the indicated level to be significantly higher than the actual level. As a result, the
water level dropped low enough to cause the reactor cooling system pump to cavitate as it
tried moving water and entrained air.
•
Prairie Island Unit 2 (MN): On February 20, 1992, the water level monitoringinstrumentation caused the indicated level to be significantly higher than the actual level.
As a result, the water level dropped low enough to interrupt the flow through the reactor’s
cooling system. It took the operators 21 minutes to re-fill the system and restart the
cooling system.
•
Sequoyah Unit 1 (TN): On March 23, 1997, the water level monitoring instrumentationcaused the indicated level to be significantly higher than the actual level.
NRC Regional Administrator Sam Collins said the special inspection team will examine how this
near-miss at Salem occurred and “
the actions the company has taken to prevent similar issues inthe future
.” This last task will be ridiculously easy because this event has happened so manytimes in the past. The true lesson from past events is in how to avoid them, not in how to repeat
them. Salem apparently learned the latter. Lightning may strike only once, but stupidity strikes
like a jackhammer. Whatever the NRC’s special inspection team finds, they need to exorcise
stupidity from all PWR sites before disaster occurs. It is foolish for the NRC to allow each site to
wait until it tempts fate before taking steps to prevent another mid-loop episode. The NRC must
act to have all PWR owners cease and desist the poor practices that cause these mid-loop nearmisses
to happen again and again.
Prepared by: David Lochbaum
Director, Nuclear Safety Project