COMMENTS TO NJPDES PERMIT NO.
0005622
CONCERNING § 316(B) OF THE
CLEAN WATER ACT
SUBMITTED BY THE MID-ATLANTIC
ENVIRONMENTAL LAW CENTER
ON BEHALF OF:
AMERICAN LITTORAL SOCIETY; CLEAN
OCEAN ACTION; COALITION AGAINST TOXICS; COALITION FOR PEACE & JUSTICE;
DELAWARE AUDUBON SOCIETY; DELAWARE RIVERKEEPER; DELAWARE SIERRA CLUB; GREEN
OCEAN SOCIETY; NEW JERSEY ENVIRONMENTAL FEDERATION; NEW JERSEY PUBLIC INTEREST
RESEARCH GROUP; NEW JERSEY SIERRA CLUB; STOCKTON PEACE ACTION; SURFERS'
ENVIRONMENTAL ALLIANCE; UNPLUG SALEM ALLIANCE
Section
316(b) of the Clean Water Act, 33 U.S.C. §1326(b), requires that the
"location, design, construction, and capacity of a cooling water intake
structure reflect best technology available for minimizing adverse environmental
impact." There is no question that Public Service Electric and Gas Co.'s
("PSE&G") Salem Nuclear Generating Station ("Salem")
SNGS is a point source with a cooling water intake structure ("intake
structure") subject to § 316(b). What is at issue is whether permit No.
NJ0005622 ("Permit") requires the design, capacity and location to
"reflect best technology available" ("BTA") for
"minimizing adverse environmental impact."
Commentators
submit that the Permit is not consistent with CWA § 316(b) for two fundamental
reasons. First, the Permit impermissibly considers costs in rejecting true BTA
at Salem. Particularly in light of last month's unanimous Supreme Court Opinion
in Whitman v. American Trucking, it is
improper for the Permit to consider the costs of BTA at all in making a BTA
determination because § 316(b) does not allow consideration of costs. Even if
costs were relevant, the Permit should have assessed the marginal increase in
costs to ratepayers for requiring BTA, instead of rejecting BTA based in part on
PSE&G's flawed comparison of total costs of conversion solely to the
commercial and recreational worth of lost fish. In any event, by disregarding
societal costs and benefits, NJDEP misapplies the cost/benefit test.
Second,
the Permit does not "reflect" BTA. NJDEP agrees that Salem is having
adverse environmental effects. Yet the Permit fails to "minimize" such
impacts. To minimize such impacts, the Permit should require a technological
conversion at Salem that adopts or reflects BTA, which is "dry
cooling," a type of technology that reduces adverse impacts by as much as
99 percent. The Permit's purported BTA conditions are not BTA. They do nothing
to reduce entrainment losses, which account for 99 percent of Salem's adverse
impact, and reduce impingement losses under the best circumstances, by only 0.2
percent.
Following
a background intended to supplement that found about the permit in NJDEP's Fact
Sheet, this comment has four parts. Part One discusses why NJDEP erred in
considering costs. Part Two supports NJDEP's findings that Salem is having
adverse environmental impacts, but disagrees that the Permit minimizes these
impacts; and, Part Three submits that Salem must adopt or reflect dry cooling --
a technology NJDEP did not consider -- because it is BTA. Part Four explains how
the design, capacity and location of Salem's intake do not reflect BTA.
I.
BACKGROUND TO NJPDES Permit No. 0005622
Along
the estuarine banks of one of the most ecologically important flyways and
ecosystems in the world, Public Service Electric and Gas Company (PSE&G)
operates the Salem Nuclear Generating Station (Salem), one of the largest
powerplants in the world. The SNGS is located along the Delaware River Estuary
at Artificial Island on the eastern shore of the Delaware River in Salem County,
New Jersey, approximately fifty miles northwest of the mouth of Delaware Bay and
thirty miles southwest of Philadelphia.[1]
Salem has two nuclear reactors, Units 1 and 2, which came on-line in 1977 and
1981, respectively.[2] Both Units 1 and 2 employ
once-through cooling. Once-through cooling results in the continuous withdrawal
of water from, and the discharge of wastewater into, the Delaware Estuary.[3]
Salem
withdraws cooling water from the estuary by means of a cooling water intake
structure virtually unparalleled in size anywhere
else in the world. The intake structure has twelve intake bays with
associated screens that rotate at an average of 0.9 inches per second, and
twelve water pumps.[4] Each pump has a capacity
of 266 million gallons per day, giving Salem a cooling water intake capacity of
3.2 BGD.[5]
After use, Salem's cooling water is discharged into the Delaware Estuary near
the New Jersey-Delaware state line.[6]
The
SNGS has been operating (and withdrawing water) under the aegis of the CWA's
National Pollutant Discharge Elimination System (NPDES) permit program since the
early 1970's. In the early 1980's, EPA delegated NPDES permitting authority to
New Jersey, and with it, authority over Salem's CWA permit. PSE&G has been
operating Salem pursuant to an NJPDES permit since September 1, 1994, which
expired August 31, 1999, but has since been administratively extended.[7]
In
1978, EPA (which at the time had permitting authority over Salem) issued a
consent decree requiring PSE&G to submit a Section 316(b) demonstration.[8]
Thereafter, EPA provided PSE&G with technical guidance to assist the
company with submission of the Section 316(b) demonstration.[9]
PSE&G subsequently submitted its first Section 316(b) demonstration
in 1984.[10]
Following delegation of the NPDES program to New Jersey in 1982, the
State undertook the task of evaluating the demonstration.[11]
On
October 3, 1990, DEP issued a Draft Permit (1990 Draft Permit) that adopted
Versar's findings, and proposed requiring Salem to convert to a closed-cycle
cooling system.[12]
On June 24, 1993, however, DEP issued a second draft permit for Salem
(1993 Draft Permit) that reconsidered the 1990 Draft Permit. The 1993 Draft
Permit proposed a mitigation experiment and associated measures in lieu of the
more stringent technology-based controls (i.e., a closed-cycle cooling system)
required by the 1990 Draft Permit.[13]
Following
extensive public comment, DEP issued a final permit (1994 Permit) on July 20,
1994, which allowed PSE&G to continue to operate Salem with little change.
The 1994 Permit's conditions ostensibly combine both technological and
mitigative means for attempting to minimize adverse environmental impacts. The
1994 Permit contains seven special conditions.[14]
NJDEP contended that three of these conditions represent compliance with Section
316(b): (1) reduction of the permitted intake flow of Salem from its maximum
design capacity to its maximum actual operating capacity;[15]
(2) modification of the design of the screens on Salem's intake structure;[16]
and (3) development and implementation of a plan to study the feasibility of
deterring fish from entering the area surrounding Salem's intake structure
through the use of underwater speakers and/or sound projectors.[17]
Non-BTA
conditions were included purportedly as further means of minimizing adverse
environmental impact.[18]
These included: (1) a wetlands restoration and enhancement program in and around
the Delaware Estuary;[19]
(2) establishment of a Management Plan Advisory Committee to provide technical
advice to PSE&G concerning the development and implementation of the
mitigation project;[20]
(3) spending at least $425,000 to build and maintain five fish ladders at
approved locations for tributaries to the estuary;[21]
and (4) conducting a baywide biological monitoring study.[22]
To help execute the biological monitoring study, DEP required PSE&G to
establish a Monitoring Advisory Committee.[23]
The Committee was empanelled to advise PSE&G regarding biological monitoring
design, implementation, modifications and results interpretation.[24]
Instead of explicitly infusing Salem's permit with a condition requiring that
Salem comply with Section 316(b) (as the New York DEC had in Hudson
Riverkeeper Fund), NJDEP required: "With respect to Section 316(b), the
Department's determination [at the time of permit reissuance, scheduled for
September 1, 1999] will include, but not be limited to, an evaluation of whether
technologies, their costs and benefits, and potential for application at the
Station have changed."[25] The 1994 permit produced
two challenges.
On
or about August 19, 1994, both the State of Delaware and a group of fourteen
environmental, conservation, and fishing interests (Coalition) appealed issuance
of the 1994 Permit.[26]
The State and the Coalition's legal arguments were, in principle,
aligned. They each argued that the
1994 Permit did not ensure that the design, capacity, and location of Salem's
intake structure reflect BTA for minimizing adverse environmental impact in
accordance with Section 316(b);[27]
that the costs of certain technology-based compliance measures not required by
DEP were not wholly disproportionate to the environmental benefits conferred by
such measures;[28] and that Salem's intake
structure was having an undue impact on interstate waters.[29]
PSE&G
settled both challenges. PSE&G's settlement with the Coalition included
requirements to reevaluate its fish screen and return systems, and evaluate
newly-developed technologies to reduce impingement and entrainment. PSE&G's
settlement with the State of Delaware's required it to spend roughly $10 million
on mitigation and restoration projects in Delaware waters over the term of the
permit. It also agreed to review Salem's intake structure problems with fish
entanglement with marsh grasses or other debris found in the intake screens and
to test new technology designed to reduce associated fish mortality if
necessary, and to fund any NJDEP review of PSE&G's evaluation of alternative
intake technologies for the Salem plant.
In March of
1999, PSE&G submitted its permit renewal application.[30]
The permit application consists of 36 volumes and 167 volumes of
reference material.[31]
Due to the large amount of materials, “[NJDEP] contracted the services of ESSA
Technologies, Ltd. of Richmond Hill, Ontario, Canada, for those issues
associated with Section 316(b) of the Clean Water Act . . .”[32]
Under the terms of its settlement, PSE&G paid for these services.
NJDEP
announced the issuance of a draft permit for public comment on or about December
28, 2000 (hereinafter, "2000 draft permit"). In the draft permit,
NJDEP "determined that [SNGS's] existing once-through cooling system in
conjunction with an intake flow limitation, an enhanced fish return system and
the study and potential implementation of a multi-sensory hybrid system
constitutes best technology available.”[33]
II.
NJDEP'S
BTA DETERMINATION MAY NOT CONSIDER COSTS AND IN ANY EVENT THE COSTS OF BTA ARE
NOT WHOLLY DISPROPORTIONATE TO THE ENVIRONMENTAL BENEFITS
CONFERRED
NJDEP
states "BTA is intended to mean the best technology available commercially
at an economically practicable cost and, further, that the costs of a technology
must not be wholly disproportionate to the environmental benefit to be gained.[34] NJDEP then posits that it
-- and not PSE&G -- shoulders the burden of demonstrating that any given BTA
is cost effective.[35]
Applying this
standard, NJDEP "determined that the Station's existing once-through
cooling system in conjunction with an intake flow limitation [Special Condition
1], an enhanced fish return system [Special Condition 2, as modified] and the
study and potential implementation of a multi-sensory hybrid system [Special
Condition 3, as modified] constitutes best technology available."[36]
NJDEP says that "the Department is committed to requiring implementation of
any cost-effective alternate technologies that will minimize impingement an/or
entrainment effects,"[37]
but evidently accepts PSE&G's position "that the costs of any [other
technological] alternatives would be wholly disproportionate to any benefits
provided," and thus that "none . . . is available for Salem."[38]
NJDEP's
use of cost considerations to influence its BTA determination is incorrect in
both invocation and application. Section 316(b) neither requires nor allows
costs considerations in making BTA determinations. Section 316(b) of the CWA
requires that an intake structure "reflect [BTA] for minimizing adverse
environmental impacts," and NJDEP engrafts onto the statute what is plainly
not there. Assuming arguendo that
costs are germane, NJDEP misapplies cost considerations by employing a
cost/benefit ratio approach instead of evaluating the marginal rate increases
ratepayers would have to bear if BTA were installed at Salem. This misstep
proves to be outcome predictive and one that avoids application of BTA at Salem.
Applying the correct cost methodology, assuming the most expensive technology
(closed-cycle cooling), complete pass-through of costs to ratepayers, and no
other sources of revenue, the maximum rate increase to PSE&G's ratepayers
would be only one and one-tenth of one
percent (1.1), or about $1.00 per month per ratepayer with an average bill of
$100.00 per month. Contrary to NJDEP's contention, legal precedent holds
that such costs are certainly not wholly disproportionate to environmental
impacts. Assuming arguendo a
cost/benefit ratio approach is allowed, NJDEP misapplies it by failing
adequately to consider societal benefits of BTA.
A. NJDEP's BTA
Determination May Not Consider Costs
In
contrast with other aspects of the CWA that specifically contemplate economic
considerations when addressing adverse environmental impacts, §316(b) allows no
such thing.[39] By omitting any reference
to costs, Congress simply did not wish for costs to be considered.[40]
Section
316(b) of the Clean Water Act requires that “the location, design,
construction, and capacity of cooling water intake structures reflect the best technology available for minimizing adverse environmental
impact.”[41] The statutory language
makes no direct or inferential reference to economic considerations. ." [42]
If Congress intended economics to be a factor in determining BTA, it would have
specifically worded the statute to do so; NJDEP may not engraft such
considerations at Salem.
The most
recent statement of controlling law reiterates this basic tenet of
administrative law that an agency may not consider costs in implementing a law
unless Congress allows it to do so. See
Whitman v. American Trucking Co. et al. (Feb. 27, 2001), 2001 U.S. LEXIS
1952, *17 (Scalia, J.)[43] In Whitman,
the Court considered whether §109(b)(1) of the Clean Air Act (CAA) allows EPA
to "consider the costs of implementation in setting national ambient air
quality standards (NAAQS) under Section 109(b)(1)."[44]
Section 109 of the CAA requires the Administrator inter alia to set primary ambient air quality standards “the
attainment and maintenance of which . . . are requisite to protect the public
health” with “an adequate margin of safety.”[45]
Respondents American Trucking argued, among other things, that the phrases
"public health" and "adequate margin of safety" allowed EPA
to consider the costs of setting the standards.[46]
By unanimous
decision, the Court disagreed and ruled that not only may
not agencies consider costs, but they must
not do so, unless Congress explicitly allows it: "the textual
commitment [to consider costs] must be a clear one.[47] Noting that the
provisions at issue "say not a word about costs," the Court said:
"we find it implausible that Congress would give to [an agency] … the
power to determine whether implementation costs should moderate national air
quality standards."[48]
(“Congress . . . does not alter the fundamental details of a regulatory scheme
in vague terms or ancillary provisions – it does not, one might say, hide
elephants in mouseholes.”[49]).
Absent language allowing consideration of costs, the Court does not even believe
it is a close call, observing:
Were it not
for the hundreds of pages of briefing respondents have submitted on the issue,
one would have thought it fairly clear that this text does not permit the EPA to
consider costs … [t]he language is 'absolute.' … Nowhere are the costs of
achieving such a standard made part of that initial calculation.[50]
Thus,
Congress does not intend for an agency to consider significant issues like costs
unless it explicitly says so. In the words of the Court, this
"unambiguously bars cost considerations … and thus ends the matter for us
as well as [an agency]."[51]
The same
holds for §316(b). It says "not a word about costs." CWA § 316(b),
like CAA § 109(b)(1), § 316(b), is a technology-forcing[52]
provision that does not allow EPA, or a state with delegated authority to issue
NPDES permits with conditions under § 316(b), to consider costs.
[53]
Nowhere is NJDEP given the power to determine whether costs should moderate
implementation of §316(b). It was improper for the agency to do so here.
That this is
so is made all the more clear by noticing, as the Court did in American Trucking, that Congress is well able to say when and how
costs may be considered. Indeed, In American
Trucking, the Court noted the string of provisions in the CAA in which
Congress allows for consideration of implementation costs.[54]
Citing a string of cases fundamental in Administrative Law, the Court thus
"refused to find implicit in ambiguous sections of the CAA an authorization
to consider costs that has elsewhere, and so often, been expressly
granted."[55]
Again, the
same holds true for §316(b) and the CWA. As with § 109(b)(1) of the CAA, CWA
§ 316(b) can easily be distinguished from other provisions that
"specifically contemplate economic considerations when addressing adverse
environmental impacts."[56] For example, Congress
required 'best technology economically achievable' in defining how effluent
standards for specified categories of pollution sources are to be created
pursuant to CWA § 301(b)(1)(A), 33 U.S.C. § 1314(b)(1)(B), and 'best available technology
economically achievable for implementing standards for discharges of toxic
pollutants. 33 U.S.C. § 1317(a). Section 316(b), however, makes no mention of
costs.
Last,
assuming the "legislative history" of a single statement linking §
316(b) and economic considerations even relevant [57]
-- which American Trucking says
it is not -- the statement does not establish whether or how costs are to be considered otherwise,
and in any event cannot be inflated to re-write the provision as enacted.[58]
B. Considering Marginal Cost Increases Attributable to BTA Would Have Supported Closed-Cycle Cooling
Assuming, arguendo
that an economic analysis is appropriate for CWA §316(b), NJDEP should have
assessed the marginal costs of BTA to ratepayers, instead of considering total
costs versus total economic benefit. EPA has applied the "wholly
disproportionate" test as a marginal
cost increase -- and not a total cost ratio -- analysis. Instead, NJ used a
total cost versus benefit ratio as the guiding principle of the "wholly
disproportionate" test. This is incorrect. Had NJDEP applied the correct
test, it would have to require PSE&G to convert to closed-cycle cooling.
A
cost-benefit analysis is clearly out of bounds.[59]
Based on the Fourth Circuit's holdings in Appalachian
Power Co. v. Train[60]
and E.I. du Pont de Nemours & Co. v.
Train,[61]
PSCO argued in Seabrook II that a BTA determination should be accompanied by a
formal cost/benefit analysis.[62]
Consistent with its own guidance, [63]
EPA found in Seabrook II, that "[t]here
is nothing in Section 316(b) indicating that a cost/benefit analysis should be
done."[64]
Instead, the
standard that EPA has applied when it has considered costs is whether the cost
of the technology to be required is wholly disproportionate to the environmental
benefit to be gained.[65]
In Seabrook II, EPA remarked that
"it is [not] reasonable to interpret Section 316(b) as requiring use of
technology whose cost is wholly disproportionate to the environmental benefit to
be gained," reasoning that "some consideration ought to be given to
costs . . . otherwise the effect would be to require cooling towers at every
plant . . . regardless of whether any significant degree of entrainment or
entrapment [impingement] was anticipated."[66]
Nonetheless,
rather than turning to a cost/benefit ratio, the "wholly disproportionate
test" requires an evaluation of the marginal
rate increase to ratepayers of BTA.[67]
EPA has ruled that § 316(b) cost considerations require consideration of the
marginal cost to each ratepayer of implementing a proposed technology, and not
the total cost of the technology to a utility.[68]
In Brunswick, for example, EPA found
that while a reduction in capacity of 96% would cost a total of $106,300,000,[69]
the monthly marginal cost to each residential ratepayer would be a mere $.77 to
$.85 per month, or an increase of approximately 2.5%.[70]
When EPA compared this 2.5% rate increase with the 96% reduction in the
adverse environmental impact associated with conversion to a closed-cycle
system, EPA concluded that "an increase of approximately 2.5% from the . .
. average monthly residential [electric] bill is not wholly disproportionate to
a 96% reduction in the severe adverse environmental impacts of the plant."[71]
Applying a
marginal cost increase test here would have established that the cost of closed
cycle cooling is not wholly disproportionate to the environmental benefits.
Indeed, applying this test, NJDEP has found that the marginal cost of closed
cycle cooling at Salem is not wholly disproportionate to environmental benefits.[72]
NJDEP has acknowledged such costs to be a mere $0.20 per month ($1989).[73]
The Permit should have considered such marginal cost increases.
Natural draft
towers save about 86% of the fish for only a 1.1% increase in revenue,
[74]
thus equating, at the most, a 1.1
percent increase in rates.[75]
Assuming the typical PECO or PSE&G ratepayer uses 1000 kWh a month and has a
monthly bill of $100, the 1.1% revenue increase needed to install natural draft
towers at Salem would translate to an per ratepayer increase of $1.10 per month,
or $13.20 per year. The Permit should have considered such marginal cost
increases. No such comparison can be attempted for dry cooling because NJDEP did
not even consider it.
C. Even Though a Cost/Benefit Test is Impermissible, NJDEP Misapplies It
In addition
to being incorrect in the first place to consider a cost/benefit analysis, NJDEP
nonetheless misapplies it. Although NJDEP makes a strong statement of its
commitment, it incorrectly accepts, without question, the economic analysis
conducted by PSE&G in support of its permit application.[76]
PSE&G contends "[a] permitting authority cannot require an alternative
as BTA when its economic and environmental costs are wholly disproportionate to
its environmental benefits."[77]
PSE&G studies six potential alternatives to the existing once-through intake
structure at Salem and finds "that, in the case of each alternative, costs
are wholly disproportionate to benefits."[78]
PSE&G submits that "NJDEP's 1994 determination that the existing fish
protections system is BTA for Salem"[79]
is correct, and that "[t]here are no additional intake technologies or
measures that are functionally suitable for adoption at Salem at an economic and
environmental cost that is not wholly disproportionate to the environmental
benefits provided."[80]
To support
its contention, PSE&G utilizes a cost-benefit ratio analysis (CBA).[81]
PSE&G's CBA calculates the cost of the alternatives by calculating:
(1) the costs associated with construction and installation; (2) incremental
operating and maintenance costs; and (3) the value of lost power at Salem as a
result of construction and changes in continuing plant operations.[82]
PSE&G
calculates the benefits of the alternatives by assigning a monetary value to the
commercial and recreational fishing benefits expected if alternatives were
implemented.[83]
The assigned values for commercial fishing range from $0.07 per pound for
Atlantic menhaden to $3.05 per pound for striped bass.[84]
The assigned value for recreational fishing is $3.52 per pound.
The estimates of pounds of fish caught commercially and recreationally
are based on 1990 to 1996 harvests.[85]
PSE&G
then estimates the total cost for natural draft towers and mechanical draft
towers to be $712.0 million and $849.2 million respectively.[86]
PSE&G estimates the benefit of implementing closed cycle cooling to be a
mere $58 million.[87]
PSE&G further calculates the cost-benefit ratio for natural draft towers to
be 12.3:1 and the ratio for mechanical towers to be 14.7:1. Applying these
figures, PSE&G concludes that closed cycle cooling is not BTA for Salem
because the costs associated with its installation are wholly disproportionate
to the environmental benefits that would be gained.[88]
NJDEP thus
concludes that the only alternative to the existing intake structure that is not
wholly disproportionate to the environmental benefits gained is the potential
installation of strobe light/air bubble curtain technology: "Therefore, the
Department, has determined that study of a multi-sensory hybrid system, of which
strobe light/air bubble is a component of, is an available technology at a cost
which is not wholly disproportionate to the environmental benefits to be
realized."[89] Nonetheless, NJDEP,
however, does not require the installation of the strobe light/air bubble
system. Instead, NJDEP curiously considers the study of a multi-sensory system
part of the BTA determination.
PSE&G's
CBA approach, however, is flawed because it fails adequately to take into
account societal benefits. Economic theory states clearly that the appropriate
level of analysis for all costs and benefits estimates is the societal level.[90]
Thus, when considering the BTA, NJDEP should have considered
"external" environmental costs of failing to implement a particular
technology.[91]
Yet, as ESSA
concludes, PSE&G's CBA is fundamentally flawed because it does not
adequately reflect societal (so-called "external") costs and benefits.[92] A study of PSE&G's
economic analysis supports ESSA's finding that the estimated costs for
installing closed cycle cooling should be from the societal perspective.[93]
"Social welfare increases when private parties who use the public's
environmental goods and services face the full cost of their actions."[94]
Anything less than full cost leaves unpaid the full cost of producing
electricity, resulting in falsely low consumer costs and a depreciated
appreciation of the environmental resources used to produce the electricity.[95]
Cost estimates from the utility perspective are much higher than from the
societal perspective.[96]
Unfortunately,
cost/benefit data used by PSE&G in their CBA "are not useful for
conducting any test of proportionality between benefits and costs."[97]
To correctly determine the price of environmental resources, both the active and
passive component of the environment must be considered.[98]
On average, for every dollar of lost active use, $1.90 of passive loss occurs.[99]
The active component consists of actual use of the Delaware Estuary recreation
such as fishing, swimming and boating. The passive component consists of two
parts, option and existence values. Option value refers to an increase in use as
conditions change, i.e., even if someone does not currently use the estuary,
they may choose to use it (and may be willing to pay more to use it) as the
environmental quality of the estuary enhances. Existence values refer to the
amount that individuals are willing to pay to preserve the estuary out of a
sense of responsibility.
PSE&G's
cost-benefit analysis is inadequate because it limits the active component and
does not address the passive component.[100]
As discussed, to calculate the benefits of closed-cycle cooling, PSE&G
simply assigns a monetary value to commercial and recreational fish caught. PSE&G
underestimates the active benefit by ignoring the value realized by fishermen
who enjoy fishing even if they do not catch anything, or practice catch and
release.[101]
This is inconsistent with the CWA. Section 101 of the CWA states:
"It is the national goal that wherever attainable, an interim goal
of water quality which provides for the protection
and propagation of fish, shellfish, and wildlife and . . . for recreation in
and on the water should be achieved"[102];
§ 316(b) of the CWA states that intake structures shall "reflect the best
technology available for minimizing
adverse environmental impact."[103]
Additionally,
the true active benefit of saving the aquatic life in the Delaware Estuary is
the enhancement to such ecosystem services as detoxification and decomposition
of waste; maintenance of biodiversity; food; recreation; and aesthetic beauty
and intellectual stimulation that lift the human spirit.[104]
Yet PSE&G does not take these (and other) passive values into account
and therefore incorrectly devalues the benefit of alternate technologies, such
as closed cycle cooling.[105]
EPA has established that as the environmental benefits associated with a
technology increase, so too do the acceptable cost levels associated with a
proposed technology.[106]
Clearly, a principal priority in the implementation of the provisions of these
laws is the protection of aquatic life and associated passive values.
Next,
incorrectly inflated costs and underestimated benefits cause PSE&G's CBA
ratios used by PSE&G to be inaccurate and artificially high, which in turn
allows PSE&G to erroneously conclude that the cost of installing
closed-cycle cooling is wholly disproportionate to the environmental benefits.[107]
Last,
NJDEP inappropriately fails to consider to what extent PSE&G had reason to
believe that such costs would be required when the plant was constructed.
For instance, during the course of the Administrator's review of the RA's
ID in Brunswick II (requiring CP&L
to reduce its intake capacity by 96%), CP&L claimed that a requirement to
retrofit the Brunswick facility would be financially prohibitive.[108]
CP&L suggested that existing cooling systems should be subject to a
different standard than new cooling systems.[109]
In response, without passing on the merits of the issue, EPA stated:
I
suggest that it would be useful for the RA to include in his revised decision, .
. . findings concerning the timing of construction of the once-through cooling
system. Specifically, did CP&L have reason to believe cooling towers might
be required when it constructed its once-through system, and if so, what
alternatives were available to it?[110]
On
notice for thirty years (since enactment of §316(b) in 1972) that a design
change, or reduced capacity, or some other technology, may in the future be
required, PSE&G should not be rewarded for ignoring that information and
should instead be held responsible for technologies that were achievable, in the
least, at the time of construction, or were foreseeable.
II.
The permit does not Minimize Adverse Environmental
Impacts
A.
Salem's Intake Structure is Having an Adverse Environmental Impact
Section
316(b) is applicable to intake structures that are having an "adverse"
environmental impact.[111]
NJDEP considers "[t]he cornerstone of PSE&G's [permit] application [to
be] the [adverse] impact assessment,"[112]
and that "[m]any of the analyses including in [PSE&G's] application
feed into [the adverse impact] assessment."[113]
EPA defines
"adverse" to mean "unfavorable, harmful, difficult, or
detrimental," but not "irreversible" or
"irretrievable."[114]
EPA maintains that any detrimental
environmental impact is "adverse,"[115]
including those inflicted by impingement or entrainment,[116]
and that "fish losses of any given
quantity" must be considered and "minimized" as required by
the CWA.[117] EPA says that such
adverse impacts occur "whenever
there is entrainment or impingement damage as a result of the operation of a
specific [intake structure]."[118]
EPA uses both short-term and long-term criterion measurements to determine the
extent of an intake structure's impact on the environment, viewing both absolute
and percentage damage.[119]
Consistently, NJDEP defines "adverse environmental impact" to be the
death of any fish: "NJDEP and other states, such as New York, have
considered the death of any fish at or
through a cooling water intake structure to be an adverse [environmental] impact
. . ."[120]
There
is no question that Salem has an adverse impact; fish losses from Salem are
astounding. The U.S. Fish and Wildlife service estimates combined loss of
finfish and blue crab as a result of the operation of Salem to be 2.9 million
kilograms per year.[121]
This translates to approximately 5.5 million weakfish, striped bass, white
perch, blueback herring, spot, over 800 million bay anchovy, and other fish due
to impingement. In addition, 3,327.9 million fish are lost due to entrainment.[122]
Worse still, USF&WS believe these figures undercount annual aquatic losses from Salem. Indeed, Salem is
responsible for adult losses for herring, spot, and white perch [that] exceed
the average commercial or recreational fishery for the Delaware Estuary for the
period of 1975-1980 stretching from Trenton to the Atlantic Ocean, 120 miles
away.[123]
NJDEP
has agreed that "the [ongoing] adverse impacts of the SNGS are large and
indicate the potential for substantial long-term population and ecosystem level
impacts is great," [124] and that the "once-through cooling system
employed at Salem adversely affects the Delaware Estuary and threatens the
protection and propagation of balanced indigenous populations."[125]
Reading
"adverse" to "consist[ ] of the harm to populations and
communities, rather than individuals . . . .," however, PSE&G disputes
that Salem is having any adverse effect.
[126]
PSE&G maintains that "adverse" requires evidence of the intake
structure causing (1) imbalance in the indigenous populations of fish, and (2)
jeopardy to the sustainability of fish stocks of Representative Important
Species (RIS).[127]
Employing this standard, PSE&G concludes that "there is no evidence
that Salem's intake structure is causing or will cause an adverse environmental
impact," and that there is "no justification or legal basis for
requiring changes at the intake."[128]
PSE&G's
position is clearly absurd.[129]
As NJDEP remarks, "PSE&G and [NJDEP] do not agree regarding the
definition of 'adverse environmental impact,'"[130]
and has determined that "it is justified in requiring the pursuit of
alternate intake protection technologies, to further minimize the impacts at the
Salem Station."[131]
NJDEP's interpretation of the term "adverse" to constitute the loss of
"any fish" is consistent with EPA's interpretation, while PSE&G's
is flatly not. As the State of Delaware's consultant commented, environmental
harm is adverse long before it causes either an "imbalance" (whatever
that means) to indigenous populations (whatever that is), or
"jeopardizes" (read, extirpate or threaten) fish stocks of species PSE&G
believes are "important."[132]
ESSA rejects PSE&G's "population approach" and the notion that an
impact is not adverse unless is causes an "imbalance" to or
"jeopardizes" fish stocks on similar grounds: [133]
Each of the
three assessment endpoints chosen in the PSE&G Application (i.e., historical
trends, long term sustainability, fish community structure) are confounded by
changes in other stressors (i.e., water quality, changes in harvest).
Inferences made on these assessment endpoints are therefore dependent on
historical and future assumptions regarding other stressors.
By contrast, assessment endpoints such as fish
killed by entrainment and impingement and foregone production, are related
directly to the impacts of the power station intakes, are less confounded by
other factors, and require fewer assumptions about unknown parameters.
ESSA says
that although "assessing impacts on the populations is necessary, [ ] it is
not sufficient."[134]
In so doing, ESSA rejects PSE&G's application of EPA's Guidelines on Ecological Risk Assessment,[135]
concluding that PSE&G misapplies the Guidance.[136]
Indeed, EPA finds that the impact of Salem's intake structure is both adverse
and underestimated.[137]
Therefore,
there is no doubt that the intake structure at Salem is having an "adverse
environmental impact" that PSE&G must "minimize."
B.
The Permit Does Not Minimize Salem's Adverse Effects
Section
316(b) requires that the "design, location, … and capacity of a intake
structure reflect best technology for minimizing adverse environmental
impact."[138] The Permit, however,
does not minimize adverse effects.
EPA
interprets the term "minimize" to mean a reduction to the
"smallest possible amount or degree." [139]
The American Heritage Dictionary defines "minimize" as: "[t]o
reduce to the smallest possible amount, extent, size, or degree."[140]
Although this standard does not require elimination of all losses of organisms
due to plant operations,[141]
minimization of adverse environmental impact is required regardless of whether
the adverse environmental impact is significant; in EPA's words, "[a]ll
environmental harm should be avoided."[142]
A
decade ago, NJDEP agreed that "[t]he only means of reducing the risk of
long-term population and ecosystem level impacts from occurring, would be to
institute major reductions in entrainment and impingement losses … at
Salem." Yet to minimize impacts, the Permit requires PSE&G (1) to limit
is withdrawal amounts to no more than the most Salem could withdraw, (2)
continue to operate a fish return system, and (3) study various techniques for
reducing impingement and entrainment.[143]
These
measures clearly do not reduce impacts "to the smallest possible amount,
extent, size, or degree." Nor does it meet the requirement that "[a]ll
environmental harm should be avoided." First, most important, the Permit requires no reduction in entrainment losses. Entrainment losses
constitute 95 percent of the intake structure's impact. The Ristroph Screens,
the Fish Return System and Sound Study are designed only to reduce impingement..[144] In any event, PSE&G's
studies on entrainment contain biases in sampling procedures that necessitate
data adjustments.[145]
Second,
the Permit does not require different technologies to minimize impacts. The
design features contemplated by Section 316(b) revolve around technologies that
will reduce fish losses due to both entrainment and impingement effects.[146]
Presently, however, the technologies used by the PSE&G SNGS largely involve
antiquated fish screening and fish return devices designed only to prevent
debris from entering the cooling water system.[147]
These systems "are limited in their abilities to minimize adverse
aquatic impact."[148]
For example, the ("enchanced") Ristoph screens at Salem do little to
protect the mortality rate of weaker species such as bay anchovy and alewife.[149]
PSE&G's application contains “inconsistencies and points of confusion in
the documentation” as it relates to impingement.[150]
Yet fish return systems remain unchanged. The intake flow limitation is the same
flow limit that was specified in the July 20, 1994 permit (3,024 million gallons
per day) and is based on "the impingement/entrainment loss estimates
presenting in the March 4, 1993 PSE&G Renewal Application Supplement . .
." [151] Other
techniques are left for future study, but not implementation.
Third,
the Permit ignores the cumulative effects of the intake structures of other
facilities in the Delaware Estuary in determining how much
"minimizing" need occur. In Brunswick
I, the Office of Regional Counsel for EPA Region IV suggested that it is
impossible to determine the impact of a single intake structure on an estuary
and its aquatic life and, therefore, that location decisions should include
consideration of the existence of other intake structures in the area.[152]
The RA in Brunswick I stated:
"The environmental decision to be made by the regulatory agency is:
at what point do we draw the line at this powerplant, or the next, or the next?
It appears that Congress has answered this question by requiring best
technology to minimize impact at all
plants."[153]
Brunswick I suggests that,
although an intake structure may appear to have little impact on populations,
the cumulative effect of many intakes "must eventually spell doom for
important marine resources."[154]
Thus, it is evident that Section 316(b) requires consideration of the
impacts of all intake structures on a source waterbody. The Permit does not do
so.
BTA TO MINIMIZE ADVERSE ENVIRONMENTAL IMPACT
What reflects BTA minimizing adverse environmental impact "is an
issue of fact."[155] BTA is "that
technology which produces the greatest reductions in damage inflicted upon
aquatic resources by entrainment and impingement."[156]
EPA maintains that "[t]he reference
point for best technology is closed cycle cooling."[157]
The United States Fish and Wildlife Services maintains that "closed-cycle
cooling [is] the best technology available" for Salem.[158]
ESSA (like Versar before it), finds that "cooling towers . . . would
minimize entrainment/impingement events . . .," as required by the CWA.[159]
The 1989 expert report prepared by Versar found that "a closed cycle
cooling system would reduce Salem's cooling water intake requirements by more
than 95% and result in a concomitant 95% reduction of entrainment and
impingement losses, "[160]
and would reflect BTA at Salem.
Fact
is, the proven best technology available for "minimizing" adverse
environmental impact is closed-cycle cooling. "[T]he only real means to
reduce fish mortality is to significantly reduce intake water flow thru the
implementation or a recirculating cooling water system . . ."[161]
Closed-cycle cooling technologies
consist of dry cooling, hybrid (wet/dry) cooling, and wet evaporative cooling
towers. Hybrid and wet evaporative cooling towers require roughly the same
amount of water intake because "the dry sections of the hybrid cooling
towers are only operated to abate plumes, and the time frame for visible plumes
is relatively small given the total number of hours of operation."[162]
These technologies reduce water withdrawal, and therefore, impingement and
entrainment losses by as much as 95 percent.[163]
The
Commentators submit that dry cooling technology in particular
"reflects" BTA and thus Salem must minimize its impact commensurate
with dry cooling. Dry cooling requires the least amount of water intake and
reduces the adverse effects of impingement and entrainment, thereby minimizing
the adverse environmental impacts.[164] Dry cooling technology
is the most effective technology for minimizing adverse environmental impacts
because it requires the least amount of water intake.[165]
The water in dry cooling systems does not come in contact with the air, rather
it travels through closed pipes in the tower.[166]
Keeping the water out of contact with the air reduces the amount of
evaporation and consequently reduces the amount of water needed. Dry cooling
systems have been installed in power plants of varying type and sizes for over
60 years.[167]
"[I]nstallations of dry cooling technology in the U.S. have been growing
rapidly since the early 1980's."[168]
"There are at least 50 power plants with dry cooling systems in operation
in the U.S. today . . ."[169]
The amount of generating capacity using dry cooling systems in the U.S. has
increased by over 15.4 percent per year between 1985 and 1998.[170]
Conversely, the amount of generating capacity using evaporative cooling systems
has increased by only 0.2 percent per year over the same time period.[171]
Dry cooling technologies reduce water withdrawal, and therefore, impingement and
entrainment by as much as 99 percent. "[Salem]
currently uses 2.1 million gallons per minute to produce 2200 MW which is
equivalent to 954 gpm/MW. Assuming a 99.98% reduction in water usage with the
use of dry cooling, water usage could be decreased to just 420 gpm or 0.19 gpm/MW."[172]
A 99.98% reduction in water usage would result in a concomitant 99.98%
reduction in impingement and entrainment events at Salem.
Importantly,
the Commissioner of the New York Department of Environmental Conservation (NYDEC)
held that dry cooling is the most recent technology, uses markedly less water
than any other intake structure, and minimizes the environmental impacts.[173]
Unfortunately, NJDEP did not consider dry cooling technologies as BTA. This is
inconsistent with §316(b). As a consultant not paid by PSE&G determined: "[U]se
of dry cooling reduces environmental impact to the greatest degree. NJDEP must
consider a dry cooling water system BTA for Salem."[174]
PSE&G
does not address dry cooling either, and discounts the possibility of installing
any closed-cycle cooling at Salem because it "would be an extremely
complicated and expensive engineering construction project."[175]
PSE&G also contends that cooling towers, as opposed to the existing intake
structure, would cause a loss in power generating capacity.[176]
"Even minor changes to the cooling water supply (for example a temperature
increase a few degrees above design or a reduction in flow) can result in a
large decrease in the Station's ability to achieve its rated capacity."[177]
But whether
the installation of the cooling towers would be complicated to install or would
result in diminished power generation capacity is not determinative under CWA §
316(b). The statute does not render installation difficulties or potential
reductions in power generation determinative of whether compliance is required.
There is no waiver for difficult jobs; indeed, there is no waiver at all.
In contrast,
none of the technologies, considered as BTA for Salem, discussed in the next
part to this comment, "can be considered BTA for minimizing environmental
impacts at the [SNGS] because they fail to address entrainment losses."[178]
As discussed supra, “once-through
cooling, even with sub-littoral intakes and fish protection devices, does not
offer equivalent levels of environmental protection to that afforded by dry
cooling.”[179] Comparison of
impingement losses versus entrainment losses using PSE&G's 1978-1982 and
1998 data show that "[f]rom 1978-1982 entrainment accounted for 99.9% of
the fish lost . . . and in 1998 entrainment accounted for 99.8% of the fish
lost."[180] The comparison results
reflect the minimal impact of reducing impingement without reducing entrainment.
"Even if impingement can [be] reduced 100%, this would save only
0.2% of the fish lost at the [SNGS]."[181]
The technologies considered BTA in the draft permit reduce impingement but do
nothing to reduce entrainment. This is inconsistent with § 316(b).
IV. THE PERMIT DOES NOT REQUIRE THAT THE DESIGN, CAPACITY AND LOCATION OF SALEM’S INTAKE STRUCTURE REFLECT BTA FOR MINIMIZING ADVERSE ENVIRONMENTAL IMPACT
Rather than
require BTA that reflects closed-cycle cooling, NJDEP determined BTA for Salem
to be the "existing once-through cooling system in conjunction with an
intake flow limitation, an enhanced fish return system and the study and
potential implementation of a multi-sensory hybrid system. . ."[182]
Regardless, the design, capacity and location of Salem's intake structure do not
reflect BTA.
A.
The Design of Salem’s Intake Structure Does Not Reflect BTA
The intake
flow limitation in the 2000 draft permit is the same volume limit (3,024 million
gallons per day (MGD)) as specified in the July 20, 1994 BTA determination. The
figure represents no actual flow reduction whatsoever.
PSE&G discharge monitoring reports demonstrate this figure merely
matches (or exceeds) the maximum current operating capacity of Salem.[183]
Indeed, the intake flow limitation is based on “the impingement/entrainment
loss estimates presented in the March 4, 1993 PSE&G Renewal Application
Supplement . . .”[184]
NJDEP has retained the same intake flow limitation as it did in the 1994 permit
based on the fact that Salem has, on average, limited its intake flow amount to
2,968 MGD.[185]
The
ultimate success or failure of a specific cooling water intake design will
depend upon the individual characteristics of a powerplant, the waterbody from
which it is drawing its cooling water, and the aquatic organisms affected by the
cooling water intake structure.[186]
Most "designs"
involve techniques to reduce impingement. These include screening devices,[187]
use of fish handling and bypass systems,[188]
pumps,[189] trash racks,[190] and behavioral barriers.[191]
Additionally, as EPA noted in Seabrook
and Brunswick I and their progeny, the "design factor contemplates
such items as fish ladders, fish buckets, improved fish screens, protective
coatings, intake depth adjustment, modified velocity caps, and sound deterrent
devices."[192]
The
most direct influence on intake structure design involves fish screening
devices. Screening and fish return
designs employed to minimize adverse environmental impact of intake structures
can be divided into three basic types: (1)
removal and return technologies, namely, traveling, disk, drum, and fixed
screens; (2) exclusion technologies, namely, wedgewire screens, perforated
pipes, radial wells, porous dikes, and artificial filter beds; and (3) diversion
and/or avoidance technologies, such as louvers, velocity caps, and physical and
hydraulic barriers, discussed below. NJDEP, however, rejects all alternate
technologies as not available at Salem, except for limited screening methods,
and a behavioral study.
The
most common intake structure configurations, like those used at Salem, have a
fish and debris removal system followed by a system that returns impinged fish
and debris back to a waterbody.[193]
The removal entry systems are usually designed with front-end, fixed-bar trash
racks to keep large debris out of the intake structure, followed by a phalanx of
traveling screens designed to prevent smaller debris from bypassing the intake
structure and clogging condenser tubes.[194]
The return systems usually involve high- and low-pressure sprays followed by
combined or separate fish and debris return troughs, which re-introduce impinged
fish and debris to their aquatic environment. The design of the fish removal and
return systems typically distinguish one intake structure from the next. Designs
of such systems include an assortment of screens, including traveling,[195] modified traveling,[196] inclined traveling,[197] Passavant,[198]
dual flow,[199] horizontal traveling,[200] fine mesh,[201]
horizontal drum,[202]
vertical drum,[203]
rotating disk,[204]
and fixed.[205] One commonality shared
by all screens is that they do not reduce entrainment and have only a limited
ability to minimize impingement losses, and are generally ineffective in their
ability to treat fish less severely than debris,[206]
a feature of Salem.
Exclusion
technologies attempt to dissuade aquatic organisms from entering the intake
structure in the first place, thereby reducing impingement and entrainment
losses. In order of general effectiveness, exclusion technologies include
wedgewire screens,[207]
perforated pipes,[208]
radial wells,[209] porous dikes,[210] and artificial filter
beds.[211]
The Permit rejects some of these, incorrectly based on application of costs and
benefits, and ignores others.
Behavioral
barriers are designed to take advantage of fish behavioral patterns which would
cause them to avoid intake structures altogether.[212]
Behavioral barriers include louvers,[213]
velocity caps,[214]
fish barrier nets,[215]
and air bubble, electrical, light, sound, cable, chain, and water jet barriers.[216]
The permit requires PSE&G to study sound deterrence and other behavioral
barriers. The principal drawback of behavioral barriers, like those in the
Permit, is that they do not reduce entrainment, and have only limited capacity
to reduce impingement losses.[217]
B.
The Capacity of Salem’s Intake Structure Does Not Reflect BTA
The intake
flow limitation in the 2000 draft permit is the same volume (3,024 million
gallons per day (MGD)) as specified in the July 20, 1994 BTA determination. The
figure represents no actual flow reduction whatsoever. PSE&G discharge
monitoring reports demonstrate this figure merely matches (or exceeds) the
maximum current operating capacity of Salem.[218]
Indeed, the intake flow limitation is based on “the impingement/entrainment
loss estimates presented in the March 4, 1993 PSE&G Renewal Application
Supplement . . .”[219]
NJDEP has retained the same intake flow limitation it did in the 1994 permit
based on the fact that Salem has, on average, limited its intake flow amount to
2,968 MGD.[220]
EPA
defines "capacity" to mean "the volume of water withdrawn through
a cooling water intake structure."[221]
There is good reason to equate capacity with volume. Doing so provides Section
316(b)'s best means of minimizing entrainment losses, and associated impingement
losses. Indeed, the principal factor in determining the amount of entrainment
damage an intake structure will have is the volume of cooling water a plant is
withdrawing from its source waterbody and the density of organisms located
within the water withdrawn.[222]
Thus, the level of entrainment caused by a given intake structure is
proportionally decreased by reducing its intake volume.[223]
Decision of the General Counsel
No. 41,
Brunswick, Seabrook, Big Bend, and
the 1980 Hudson River Agreement have each followed this reasoning. In Decision
of the General Counsel No. 41, the EPA General Counsel employed the Random
House Dictionary definition of "capacity."
EPA quoted "capacity" to mean "cubic contents; volume;
that which can be contained."[224]
The EPA Office of General Counsel also posited that "the volume [of water]
withdrawn is the principal determinant
of entrainment damage which is the major adverse environmental effect associated
with most cooling water intake structures."[225]
The EPA Office of General Counsel noted that the major adverse environmental
impacts of intake structures are those affecting aquatic organisms in the water
drawn through the cooling system, and that such adverse impacts may be reduced
by restricting capacity.[226]
The EPA Office of General Counsel found that the legislative history of the CWA
supported its decision.[227]
In In re Central Hudson Gas & Electric
Corp., the EPA Office of General Counsel reinforced its findings.[228]
Next,
in Brunswick I, EPA stated that
"one of the most effective methods that can be used to reduce [entrainment]
impact is the reduction of volume of water withdrawn."[229]
In Brunswick I, EPA considered what
would constitute BTA for the Brunswick powerplant located on the Cape Fear River
near Wilmington, North Carolina. The Brunswick plant uses once-through cooling
and has an intake capacity of eighty-one cubic meters per second (approximately
1.85 BGD).[230]
In Brunswick I, EPA initially
decided that BTA mandated a permanent capacity restriction.[231] After the utility
challenged this decision, EPA ultimately required that the plant reduce its
flows during part of the year.[232]
The Regional Administrator held that "[t]he best technology available to
minimize the adverse environmental impacts of the plant is to restrict the
capacity of the plant's intake structure."[233]
Accordingly, EPA required CP&L to both institute seasonal flow reductions
during periods when entrainment of larval forms would be highest,[234]
as well as upgrade screening.
The
powerplant in Big Bend was able to
meet Section 316(b) requirements by implementing a 36% reduction in intake water
volume and installing fine mesh screens.[235]
Big Bend powerplant Units 1-3, were designed for once-through cooling. The
intake flow water withdrawal capacity for the station's Units 1-3 was 70.8 m3/sec
(approximately 1.6 BGD). EPA found that the intake capacity did not reflect BTA
because of the facility's entrainment effects on the bay.[236]
Therefore, EPA required the utility to reduce the intake flow by more than
one-third to 45 m3/sec (approximately 1.03 BGD).[237]
When the utility proposed to add another unit to the site, which would
have increased total intake volume to 61 m3/sec (approximately 1.39
BGD),[238]
EPA required the utility to place a fine mesh screening apparatus on two of the
four units, and to monitor their performance.[239]
The
1980 Hudson River Agreement required periods of reduced flow, partial power
output reduction and seasonal shut-downs over substantial portions of the year
during those times when aquatic organisms were most affected by the entrainment
impact of the intake structure.[240]
The restrictions were to be attained by complete unit outages.
These outages were potentially coincident with the peak summer electric
demands, and were not at times that would be economically more convenient to the
utilities. The settlement also included modifications at several plants to
further reduce adverse environmental impacts and the operation of a hatchery.[241]
In
Seabrook II, the powerplant employed a
design intake capacity of 1.2 billion gallons per day and a design intake
velocity of one foot per second.[242]
Because the powerplant operated at substantially less than full design capacity,
EPA determined that actual capacity was not large enough to require further
reduction in flow to meet BTA.[243]
Nonetheless, some utilities seeking NPDES permits have repeatedly attempted to
redefine "capacity" as the intake velocity. Each time this canard has
been served, as in Decision of the General
Counsel No. 41, In re Central Hudson
Gas & Electric Corp., and Seabrook
II, EPA has rejected it.[244]
For example, in Decision of the General
Counsel No. 41, EPA found that "capacity does not refer to the velocity
of water withdrawn through a cooling water intake structure,"[245]
nor is it limited to the physical size of the inlet of a cooling water intake
structure.[246] An interpretation that
narrows the definition of "capacity" to velocity alone (to the
exclusion of volume) would effectively remove capacity as a potential factor
meaningfully reducing adverse environmental impacts.
As
in Brunswick and Seabrook II, an agency may restrict the capacity of a cooling water
intake structure to such an extent that use of closed-cycle cooling would be a
"predictable consequence of the capacity limitation."[247]
For instance, Brunswick I involved an
intake structure with an intake capacity of 1.85 billion gallons per day,
located in an estuarine environment.[248]
After considering the impingement and entrainment effects the powerplant was
having on the aquatic organisms in its source waterbody, the RA determined that
the capacity of the plant did not fulfill the BTA requirements of Section
316(b).[249] Information provided by
CP&L indicated that use of closed-cycle cooling at the plant would provide a
96% reduction in its intake capacity.[250]
As a result, based on Decision of the
General Counsel No. 41, the RA determined that BTA for the Brunswick intake
structure could be achieved by reducing the plant's intake capacity by an amount
approximating 96%.[251]
Most
recently, in Athens, the NYDEC
Commissioner, applying Brunwsick I,
reasoned that "capacity" in CWA § 316(b) refers to "the volume
of water withdrawn through a cooling water intake structure."[252]
In Athens, the Commissioner considered
whether to require the installation of a hybrid cooling system or dry cooling.
The Commissioner found that a hybrid system required an average 4.2 mgd to
operate while a dry cooling system at the same location would require only 0.18
mgd.[253]
"I cannot discount the uncontroverted facts that application of dry
cooling would use markedly less water and reduce the adverse effects of
entrainment, thereby minimizing adverse environmental impacts to a greater
degree that a hybrid cooling system."[254]
The Commissioner subsequently directed the draft SPDES permit to be revised to
limit the capacity of the intake structure to 0.18 mgd, i.e. to
"reflect" dry cooling.[255]
Closed-cycle
cooling technologies use considerably less water than once-through cooling
systems,[256] which in turn reduces
the incidents of aquatic life impingement and entrainment.
“[I]t is impossible to remove any significant volume of water from . .
. a river . . . without also removing some of the organisms that are living
within it.”[257]
“[O]nce-through cooling, even with sub-littoral intakes and fish protection
devices, does not offer equivalent levels of environmental protection to that
afforded by dry cooling.”[258]
Because once-through cooling stations use extremely large volumes of water,
there is no once-through technology available that can ensure the level of fish
protection that is achieved with less consumptive forms of closed-cycle cooling.[259]
C.
The Location of Salem’s Intake Structure Does Not Reflect BTA
Intake
structures must be located so as to minimize adverse environmental impact. EPA
maintains that the "location" of an intake structure "can be the
most important consideration relevant to applying the best technology available
for cooling water intake structures."[260]
When cooling water intake structures draw water from a source waterbody, they
also pull into the system all of the organisms living within that water.
"The quantities of life destroyed by impingement on the screens or
entrainment through the condenser cooling system are a direct function of the
density of organisms residing in the source water[body]."[261]
Therefore, by locating an intake structure where the quantity of aquatic
organisms is high, a powerplant inevitably increases the adverse environmental
impacts it will have on the source water.
EPA
says that decisions concerning the location of a intake structure require an
"extensive ecological survey in the vicinity of the proposed site."[262]
This survey should be used to determine the potential impacts an intake
structure may have "to important wildlife and aquatic breeding, nursery,
feeding, and/or migration areas," and it may "enable determinations to
be made with regard to concentrations of aquatic life within specific and
proposed siting areas."[263]
EPA makes clear that determinations regarding the location of an intake
structure are dependent on the physical characteristics of the source waterbody
to be used as well as hydraulic and economic factors.[264]
Under
Section 316(b), "location factors primarily concern the siting or alternate
placement of the intake structure with respect to the affected
environment."[265]
Siting and alternate placement issues involve proximity to estuaries and the
cumulative impact of other intake structures, as the following paragraphs
explore in greater detail.
While
few generally applicable rules exist regarding Section 316(b) and its BTA
requirements, one general rule has been stressed by EPA (intake structures
should be located so as to avoid highly productive biological areas and
estuarine environments.) EPA says
that when considering the location of a intake structure for minimization of
adverse environmental impacts, permit writers should avoid spawning areas, fish
migration paths, shellfish beds, and locations where aquatic life is
concentrated.[266] Additionally, EPA has
made clear that a proposed intake structure should be placed at a depth so as to
avoid aquatic life.[267]
EPA followed this reasoning in Seabrook,
Brunswick, the 1980 Hudson River
Agreement, and Big Bend.
In
Seabrook II, the powerplant was
located near Hampton Harbor Estuary, about two miles from the Atlantic Ocean.[268]
In upholding once-through cooling as constituting BTA, EPA noted that
"the general design and location of Seabrook Station's intake and discharge
offshore, and not in an estuary, were . . . special considerations that have
been factored into the environmental characteristics of the area."[269]
In the extensive Section 316(b) proceedings in Seabrook, the EPA Administrator cautioned that the "conclusions
[are] based on the . . . ecology of this area . . . and [are] not transferable
to another area with different, and its own special, environmental
characteristics. . . . [I]ntake and discharge offshore, and
not in an estuary, are also special considerations."[270]
The SNGS is, of course, in an estuary.
In
Brunswick I, the "intake canal (a
part of its intake structure) beg[an] in a dredged ship channel (a migratory
pathway for aquatic organisms), interrupt[ed] a tidal creek (another migratory
pathway), and cut[] across 6,000 feet of highly productive marshland (a nursery
area)."[271]
In addition to the fact that the intake structure was located in such a
highly productive area, the intake canal was attracting populations of fish
which exacerbated the entrainment and impingement impacts created by the intake
structure.[272]
As a result of its location in these highly productive biological areas,
the RA determined that the Brunswick intake structure was having significant
adverse impingement and entrainment impacts on the source waterbody and,
therefore, that the location of the Brunswick intake structure did not comply
with the requirements of Section 316(b).[273]
EPA noted that
[t]he
proper location of intake structures is the most important consideration
relevant to applying best technology available for cooling water intake
structures. Careful location of intake structures can greatly minimize adverse
environmental impacts. For example,
intake structures should be located to withdraw water from areas that are the
least productive biologically and contain the lowest population densities of
critical aquatic organisms. Additionally,
they should be located to avoid spawning areas, nursery areas, fish migration
paths, shellfish beds, or any location containing a high concentration of
aquatic life.[274]
EPA
later reiterated its support for this position in the Brunswick Memorandum.[275]
The 1980 Hudson River Agreement involved powerplants along the Hudson River
estuary, and was concerned with long-term regional population, forage organism
and food web impacts.[276]
In making its initial BTA decision, EPA focused on the impacts of the facility
on aquatic life in the affected area and required these powerplants to institute
closed-cycle cooling.[277]
In Big Bend, EPA took note of the
sandy, tidal-swept nature of the estuary subject to impact by the intake
structure in making its Section 316(b) determination.[278]
EPA's
focus on fish population, forage, and food web impact stresses the importance of
avoiding the siting of intake structures near spawning areas, fish migration
paths, or any location with a particular concentration of aquatic life. Poor
location may cause adverse environmental impacts that may be offset only by a
reduction in intake capacity, and by improved design, discussed supra.
CONCLUSION
Commentators
respectfully submit that NJPDES draft permit NJ0005622 is not consistent with §
316(b) of the CWA. First, the Permit impermissibly considers costs in rejecting
true BTA at Salem. Particularly in light of last month's unanimous Supreme Court
Opinion in Whitman v. American Trucking,
it is improper for the Permit to consider the costs of BTA at all in making a
BTA determination because § 316(b) does not allow consideration of costs. Even
if costs were relevant, the Permit should have assessed the marginal increase in
costs to ratepayers for requiring BTA, instead of rejecting BTA based in part on
PSE&G's flawed comparison of total costs of conversion solely to the
commercial and recreational worth of lost fish. In any event, by disregarding
societal costs and benefits, NJDEP misapplies the cost/benefit test.
Second,
the Permit's does not "reflect" BTA. NJDEP agrees that Salem is having
adverse environmental effects. Yet the Permit fails to "minimize" such
impacts. To minimize such impacts, the Permit should require a technological
conversion at Salem that adopts or reflects BTA, which is "dry
cooling," a type of technology that reduces adverse impacts by as much as
99 percent. The Permit's purported BTA conditions are not BTA. They do nothing
to reduce entrainment losses, which account for 99 percent of Salem's adverse
impact, and reduce impingement losses under the best circumstances, by only 0.2
percent.
Respectfully
submitted,
James
R. May
Executive
Director, Center
Director,
Clinic
Scott
Fazio (student intern, 2000-01)
Glenn
Elters (student intern, 1999-00)
[1] Wastewater Facilities Regulation Program, Department of Environmental Protection and Energy, State of New Jersey, Draft NJPDES Permit Renewal Including Section 316(a) Variance Determination and Section 316(b) BTA Decision: NJPDES Permit No. NJ0005622, Fact Sheet at 7 (June 24, 1993) [hereinafter 1993 Salem Fact Sheet].
[2] Id. at 8.
[3] Id. at 7-8. PSE&G's permit also allows it to discharge 17,000 gallons per day of low level radioactive liquid waste. Id. at 9.
[4] Id. at 11.
[5] Id.
[6] Id. at 7-8.
[7] Department of Environmental Protection, State of New Jersey, Discharge Permit, PSE&G, Permit No. NJ0005622 at cover sheet (July 20, 1994) [hereinafter 1994 Salem Discharge Permit].
[8] Id. at 103. Incidentally, EPA at the time deferred taking action on PSE&G's Section 316(a) variance request until after a decision was made regarding PSE&G's Section 316(b) demonstration. Id. at 104.
[9] Thereafter, EPA assembled a Technical Advisory Group comprised of various federal and state scientific personnel to assist PSE&G with developing a plan of study for the Section 316(b) demonstration to evaluate Salem's impingement and entrainment effects. Id
[10] Id. at 107.
[11]
In early 1986, DEP commissioned Versar, Inc. (formerly Martin Marietta
Environmental Systems), a highly-regarded environmental consulting firm.
Versar has been retained by the Delaware Estuary Program (DELEP) to
analyze PSE&G's 1984 316(b) demonstration.
The DELEP is composed of state and local governmental, industrial
(including representatives of PSE&G), and environmental interests to
assist with the development of the DELEP's Estuary Management Plan. Id.
at 108. Thereafter, in late 1986, Versar published its findings.
Versar, Technical Review and
Evaluation of Thermal Effects Studies and Cooling Water Intake Structure
Demonstration of Impact for the Salem Nuclear Generating Station Final
Report [hereinafter 1986 Versar
Report].
The 1986 Versar Report concluded that Salem's existing once-through cooling operation was having a significant impact upon the Delaware Estuary and its aquatic life due to impingement and entrainment. Versar correspondingly recommended that DEP require PSE&G to retrofit Salem with closed-cycle cooling towers. See generally 1986 Versar Report. PSE&G contested the findings of the 1986 Versar Report. Thus, in 1987, DEP convened a technical workshop and conducted public hearings to try to resolve the dissonance between the 1986 Versar Report and PSE&G's 1984 Section 316(b) demonstration. Salem Fact Sheet, supra. Correspondingly, in 1988, PSE&G submitted written comments which provided new data and analyses not submitted previously with its 1984 Section 316(b) demonstration and, therefore, not considered by the 1986 Versar Report. Id. at 109.
[12] 1993 Salem Fact Sheet, supra.
[13] Department of Environmental Protection, State of New Jersey, Draft Discharge Permit, PSE&G, Permit No. NJ0005622 [hereinafter 1993 Salem Discharge Permit]. DEP did so over the objections of its project manager for Salem, who argued against any such mitigation experiment and in favor of a closed-cycle cooling system. See Letter of Richard Delgado to Leroy T. Cattaneo, May 23, 1989 (on file with the authors).
[14] Clearly DEP believes that the special conditions are the bulwark of the permit. The 1994 Permit requires PSE&G to set aside an irrevocable letter of credit of $20 million in trust to ensure completion of the special conditions. 1994 Salem Discharge Permit.
[15] 1994 Salem Discharge Permit, supra. Salem's permit limits average daily intake flow to 3.024 BGD, calculated using a monthly average rate. Id. Unfortunately, however, DEP's use of the phrase intake flow limitation is somewhat deceptive. In fact, 3.024 BGD matches Salem's maximum flow requirement, and represents no reduction whatsoever either in entrainment, impingement, or water withdrawal from the Delaware Estuary.
[16] Id. Salem's permit requires PSE&G to install a new fish bucket design including an inwardly placed lip extended to prevent fish escape, smooth woven mesh screens with rectangular pore openings to reduce injury to impinged fish, and a 30-inch wide fish sluiceway with a 3-inch deep water reservoir to facilitate fish return. Id.
[17] Id. at 26. Salem's permit requires PSE&G to study behavioral means of deterring fish from the intake structure through use of underwater speakers and/or sound projectors. Id.
[18] See generally Department of Environmental Protection, State of New Jersey, Response to Comments, PSE&G, NJPDES/DSW Permit No. NJ0005622 at 5 (1994).
[19]
Id. at 19-20.
The wetlands restoration and enhancement program requires PSE&G
to:
(1)
[R]estore [at least] 8,000 acres of [a] diked wetlands (including salt hay
farms, muskrat impoundments and/or agricultural impoundments) to normal
daily tidal inundation so as to become functional salt marsh; and/or [b]
wetlands dominated by common reed (Phragmites
australis) to primarily spartina
species with other naturally occurring marsh grasses. . . .
No less than 4,000 of the 8,000 acres required to be restored must
have been diked wetlands. . . .
(2)
[R]estore an additional 2,000 acres of wetlands . . . and/or preserve in a
state that precludes development through appropriate title ownership or [c]onservation
[r]estriction of no less than 6,000 acres of [upland buffers; and] . . . .
(3)
[I]mpose a [c]onservation [r]estriction [in favor of DEP on] approximately
4,500 acres of land in Greenwich Township, Cumberland County, commonly known
as the Bayside Tract. Id.
[20] Id. at 24.
[21] Id. at 24-25.
[22] Id. at 26. As part of the biological monitoring study PSE&G must complete: (1) comprehensive thermal monitoring and performance of biothermal assessment on representative important species; (2) baywide aquatic abundance monitoring; (3) impingement and entrainment monitoring; (4) abundance monitoring for ichthyoplankton and juvenile blueback herring and alewife in connection with fish ladder sites; (5) detrital production monitoring; and (6) residual pesticide release monitoring, and other studies as DEP may require. Id. at 26-27.
[23] Id. at 27.
[24] Id.
[25] Id. at 31.
[26] Letter from James R. May, Associate Professor of Law and Director of the Environmental Law Clinic, Widener University, to Office of Legal Affairs, Department of Environmental Protection and Energy, State of New Jersey 10-11 (Aug. 19, 1994) (request for an adjudicatory hearing) (on file with NJDEP). The Coalition included the American Littoral Society, Delaware Riverkeeper Network, Central Jersey Anglers, Clean Ocean Action, Del-AWARE Unlimited, Inc., Delaware Audubon Society, Delaware Bay Waterman's Association, Delaware Nature Society, Delaware River Fisherman's Association, New Jersey Environmental Federation, New Jersey Public Interest Research Group, Raymond Proffitt Foundation, Venatores Gun Club, and Watch Our Waterways. Id.
[27] PSE&G/Salem Coalition, Settlement Agreement, at 2 (Mar. 17, 1995) [hereinafter Salem Coalition Settlement Agreement].
[28] Id.
[29] Id.
[30] State of New Jersey Department of Environmental Protection and Energy, Division of Water Quality, Fact Sheet for a Draft NJPDES Permit Including Section 316(a) Variance Determination and Section 316(b) Decision: NJPDES Permit No. NJ0005622, Fact Sheet at 6 (December 8, 2000) [hereinafter 2000 Salem Fact Sheet].
[31] Id.
[32] Id.
[33] Id at 77 (emphasis deleted).
[34] 2000 Salem Fact Sheet at 65. See id. at 4 ("Although the plain language of the Act does not call for economic analysis when requiring BTA, legal precedent has provided that any BTA imposed may not be wholly disproportionate from the environmental benefits to be gained.")
[35] Id. at 69.
[36] Id. at 77.
[37] Id. at 69.
[38] Id. at 68.
[39] EPA has noted that "[t]here is nothing in § 316(b) indicating that a cost/benefit analysis should be done," whereas with regard to "best practicable control technology currently available" and "best available technology economically achievable Congress added express qualifiers to the law indicating a requirement for [an implementing agency to perform] a cost/benefit analysis." Seabrook II, 10 Env't Rep. Cas. (BNA) at 1261. EPA acknowledges that how costs are to be considered is not clearly evident: "[W]hen Congress intended for costs to be considered under the [Clean Water Act], Congress so stated." Brunswick I, at 32 (Initial Decision re: Permit No. NC007064). For example, Section 304 uses the phrase "best technology economically achievable in defining how effluent standards for specified categories of pollution sources are to be created, pursuant to Section 301(b)(1)(A)." 33 U.S.C. § 1314(b)(1)(B). See also 33 U.S.C. § 1311(b)(1)(A). Again, in Section 307, when discussing effluent limitations for toxic pollutants, Congress used the phrase, "best available technology economically achievable." 33 U.S.C. § 1317(a). Comparatively, no where within the language of Section 316(b) is any reference made to consideration of costs. 33 U.S.C. § 1326(b).
[40] To be sure, it could be argued that Congress has already taken costs into account. In its first annual report to Congress in 1974, EPA estimated that achieving a zero discharge of thermal pollutants by 1983 [as required by the CWA] would increase consumer electric bills by only 1.7% to 6.1%. Rabago, supra note 42, at 458. In contrast, in 1977, the steam electric generating industry completed a study which concluded that substantial reduction in cooling water volume could increase consumer electric bills by as much as 10%. Id. at 458-59. However, "when considering all technologies available to the industry, even [the] `worst case scenario' [envisioned by the utility industry] represented less than a one percent increase in capital expenditures, operating and maintenance expenses, and annual revenue requirements." EPA thus tried to establish that control of thermal discharges and concomitant reductions in adverse environmental impacts by [intake structure] could be achieved by converting existing cooling systems to closed-cycle cooling systems without undue economic impact. Id.
[42] Hudson Riverkeeper Fund, Inc. v. Orange & Rockland Utils., Inc., 835 F. Supp. 160, 166 (S.D.N.Y. 1993) (determining that the language of Section 316(b) was clear and therefore the plain meaning of the provision controls its construction).
[43] Whitman
v. American Trucking Association, et al (Feb. 27, 2001), 2001 U.S. LEXIS
1952, *17.
[44] Id. at *12.
[45] Id. at *7.
[46] Id. at *12.
[47] Id. at *17.
[48] Id. at *18.
[49] Id. (Citations omitted.)
[50] Id. at *12.
[51] Id. at *22.
[52] See generally The Quick and The Dead at 471. See also Whitman at 56 (concurring opinion) ("[t]he legislative history shows that Congress intended the statute to be technology forcing.").
[53] Whitman v. American Trucking at 17.
[54] Id.
at *16. Citing CAA §108(b)(1) requires "information on air pollution
control techniques, which information shall include data relating to the
cost of installation and operation."
42 U.S.C. § 7408(b)(1).
CAA §109(d)(2)(C)(iv) "requires the Clean Air Scientific
Advisory Committee to 'advise the Administrator of any adverse public
health, welfare, social, economic, or energy effects which may result from
various strategies for attainment and maintenance.'"
42 U.S.C. §7409(d)(2)(C)(iv).
[55] Id. at 17 (citations omitted.)
[56] The Quick and The Dead at
472.
[57] See, e.g., 41 Fed. Reg. 17,387, 17,388 (1976); Seabrook II, 10 Env't Rep. Cas. (BNA) at 1261 (citing A Legislative History of the Water Pollution Control Act Amendments of 1972, 93d Cong., 1st Sess. (1973)).
[58] As EPA has noted: "Indeed, but for one bit of legislative history, there would be no indication that Congress intended costs to be considered under Section 316(b) at all." Seabrook II, 10 Env't Rep. Cas. (BNA) at 1261; Brunswick I, at 32 (Initial Decision re: Permit No. NC007064) (citing A Legislative History of the Water Pollution Control Act Amendments of 1972, 93d Cong. 1st Sess. 264 (1973)).
[59] Seabrook II, 10 Env't Rep. Cas. (BNA) at 1261; Brunswick I, at 31-32 (Initial Decision re: Permit No. NC007064).
[60] Appalachian Power Co. v. Train, 545 F.2d 1351, 1378 (4th Cir. 1976).
[61]
E.I. du Pont de
Nemours & Co. v. Train, 541 F.2d 1018, 1030
(4th Cir. 1976).
[62] CWA Section 304(b)(1)(B) provides that a cost/benefit analysis is: “the total cost of the application of technology in relation to the effluent reduction benefits to be achieved from such application. 33 U.S.C. § 1314(b)(1)(B).
[63] 41 Fed. Reg. 17,387, 17,388 (1976).
[64] Seabrook II, 10 Env't Rep. Cas. (BNA) at 1261; accord 41 Fed. Reg. 17,387, 17,388 (1976).
[65] EPA first articulated this standard in Seabrook II, 10 Env't Rep. Cas. (BNA) at 1261; Brunswick I, at 61 (Initial Decision re: Permit No. NC007064).
[66] Id.
[67] See, e.g., Brunswick I, (Initial Decision re: Permit No. NC007064).
[68] Id. at 63.
[69] Id. at 63.
[70] Id. at 69.
[71] Brunswick I, at 69 (Initial Decision re: Permit No. NC007064).
[72] 1989 Versar Report at VII-23.
[73] Id.
[74]
Id. at 2.
[75] Id. at 9. "The ratios are not predictions of future changes in electric bills because there are different classes of customers (wholesale or retail, or regulated or deregulated); and, ratemaking is a complex procedure involving allowable costs and their timing allocated over different classes of customers."
[76] See generally id. at 69 ("Department's Review of Cost/Benefit Analysis and Requirements regarding Alternate Intake Protection Technologies").
[77] PSE&G Memo in Support of Permit Application at 158.
[78] Id. PSE&G alternatives to the existing once-through intake structure considered by PSE&G include: (1) wedge-wire screens, (2) dual-flow fine mesh screens, (3) modular inclined screens, (4) strobe light/air bubble curtain combination, (5) flow reduction alternatives (including seasonal flow reductions and revised refueling outage schedules), and (6) retrofitting with closed-cycle cooling.
[79] Id.
[80] Id. at 164.
[81] Id. at 166.
[82] Id. at 159.
[83] Id. at 160
[84] Id. at 163.
[85] Id.
[86] Id. at 166.
[87] Id.
[88]
PSE&G contends that the CBA used is conservative because: (1) the
analysis does not account for added environmental costs (such as the cost of
increased air pollution that would be recognized by society as a result of
fossil fuel plants having to compensate capacity during any SNGS shutdown
for installation; (2) the analysis overestimates because it does not account
for a recent decline in fish prices; and (3) the analysis ignores increased
commercial fishing costs which may reduce or eliminate the commercial
fishing benefits. Id.
[89] Id. at 169.
[90] ESSA Report at 59.
[91] The "external costs" associated with cooling water intake structures are addressed in Richard L. Ottinger et al., Pace University Center for Environmental Legal Studies, The Environmental Costs of Electricity (1989). See also Richard L. Ottinger, Getting at the True Cost of Electric Power, Electricity Journal (July 1990); Faith Halter & Joel T. Thomas, Recovery of Damages by States for Fish and Wildlife Losses Caused by Pollution, 10 Ecology L.Q. 5 (1982).
[92] Id.
[93] Comments on the Salem Cooling Water Intake Analysis, Dr. Michael Kavanaugh (February 20, 2001) at 1 [hereinafter referred to as Kavanaugh]. Dr. Kavanaugh is an economist with 25 years of experience applying economic principles to environmental and natural resource issues.
[94] Id. (citing the 1994 Economic Report of the President).
[95] Id.
[96] ESSA Report at 52.
[97] Kavanaugh at 2.
[98] Id.
[99] Id. (citing T.C. Brown in "Benefits and Costs of Transfer in Natural Resource Panning", John Bergstrom (1993)).
[100] Id.
[101] Id. at 6.
[102] 33 U.S.C. § 1251(a)(2) (1988) (emphasis added). Some state laws contain similar overtures. The New Jersey Water Pollution Control Act (NJWPCA), N.J. Stat. Ann. § 58:104-12 (1994) states: "It is the policy of this state to restore, enhance and maintain the chemical, physical and biological integrity of its waters, to protect public health, to safeguard fish and aquatic life and scenic ecological values, and to enhance the ... recreational . . . and other uses of water." N.J. Stat. Ann. § 58:10A-2 (emphasis added).
[103] 33 U.S.C. § 1326(b) (emphasis added).
[104] Id. at 5.
[105] Id. at 8.
[106] Seabrook IV, No. 76-7, 1978 NPDES LEXIS 15, at *68.
[107]
See generally, Kavanaugh.
[108] Brunswick II, Appeal No. 77-19, 1978 NPDES LEXIS 4 at *9 (EPA Feb. 20, 1978).
[109] Id.
[110] Id. at 9. The only record of the RA's remanded opinion was found in the Brunswick Historical Summary which stated that the RA "submitted a supplement to the ID which resulted in no change in the decision put forth in the ID." Region IV, EPA, Brunswick Historical Summary and Review, at 3 (on file with the Widener University School of Law, Environmental Law Clinic).
[111] See e.g., Brunswick I, Region IV, EPA 28 (Nov. 7, 1977) (Initial Decision re: Permit No. NC0007064).
[112] 2000 Salem Fact Sheet at 70.
[113] Id.
[114] See, e.g., Brunswick I, at 28, 31 (Initial Decision re: Permit No. NC007064) (citing Webster's Third New International Dictionary (1976)).
[115] 38 Fed. Reg. 34,410 (1973) (to be codified at 40 C.F.R. pts. 401-402) (proposed Dec. 13, 1973).
[116] 1977 Adverse Impact Guidelines. See also, 65 FR 49059, National Pollutant Discharge Elimination System, Cooling Water Intake Structures for New Facilities, Proposed Rules, August 10, 2000.
[117] Id. at 1 (emphasis added).
[118] Id. at 15 (emphasis added).
[119] To determine the extent of adverse impact, EPA considers six factors: (1) absolute damage (i.e., the number of fish impinged or percentage of larvae entrained on a monthly or yearly basis); (2) percentage damage (i.e., the percent of existing fish and/or larval populations impinged or entrained); (3) absolute and percentage damage to endangered species; (4) absolute and percentage damage to any critical aquatic organisms; (5) absolute and percentage damage to commercial and/or sport fisheries yield; and (6) whether the impact jeopardizes the protection and propagation of shellfish and fish (i.e., the long-term impact). Id. Consonant with this guidance, the Permit requires PSE&G to conduct "a further analysis of losses at the [SNGS]." Fact Sheet at 72, the objectives of which are:
- The biomass lost to the ecosystem should be calculated either using a slightly modified version of the production foregone model for all RIS or the spreadsheet approach.
- The contribution of RIS other than Bay Anchovy to the forage available for commercial and recreationally important species should be examined.
- A more detailed analysis of the levels of uncertainty in the production and catch forgone estimate needs to be considered.
- The estimates used for the survival rates of Age 0 - Blueback Herring should be revised.
- The base entrainment and impingement mortality estimates should be compared against the historical averages to ensure consistency.
- Projected increases in RIS abundance should be included in the estimates of catch and production forgone.
- The
potential to customize intake protection strategies to minimize the impact
of the plant on catch forgone and the biomass lost to the ecosystem should
be further investigated.
[120] Id. (emphasis added).
[121] United States Department of the Interior Fish and Wildlife Services June 30, 2000, comments to NJDEP draft NJPDES permit for PSE&G's SNGS at 3.
[122] Id. Accord, 1989 Versar Report at VII-26. (The 1989 Versar Report estimated that Salem is responsible for annual net productivity losses of 17,909,400 pounds of bay anchovy, 11,448,890 pounds of weakfish, and 38,969 pounds of white perch.[122] This translates into 800 million bay anchovy, 1 million weakfish, 300,000 spot, 200,000 blueback herring, and countless other organisms.)
[123] Id. at V-27.
[124] The 1989 Versar Report notes that any deficiencies in either the 1986 or the 1989 Report are a result of the many inadequacies of PSE&G's submissions. Versar, Technical Review and Evaluation of Thermal Effects Studies and Cooling Water Intake Structure Demonstration of Impact for the Salem Nuclear Generating Station at VI-4 (Jan. 1989) (Revised Final Report) [hereinafter 1989 Versar Report].
[125] Id. at VI-1. In particular, the 1989 Versar Report maintained that the entrainment and impingement of aquatic life resulting from the operation of the intake structure at Salem significantly effects: (1) important spawning and nursery functions for RIS; (2) the food web of the Delaware Estuary; and (3) the commercial and recreational fishing uses of the Delaware Estuary. Id. at VIII-1.
[126] PSE&G Memo in Support of Permit Application (3/4/1999) at 16 [hereinafter 1999 PSE&G Memo].
[127] Id.
[128] Id. at 18.
[129] See Comments of C. Phillip Goodyear at 1 (expressing "philosophical problems with [PSE&G's] assumptions [that Salem] … is having no effect.).
[130] 2000 Salem Fact Sheet at 70.
[131] Id.
[132] See Goodyear comments, at 1 (disagreeing with PSE&G theory that "if species don't exhibit declines towards extinction, then there's no deleterious impact.") thru 4.
[133]ESSA, Review of Portions of New Jersey Pollutant Discharge Elimination System (NJPDES) Renewal Application for the Public Service Electric & Gas’ (PSE&G) Salem Generating Station at 75 (June 14, 2000) (Final Report) [herinafter ESSA Report].
[134] Id.
[135] 63 Fed. Reg. 26846 (May 14, 1998).
[136] ESSA Report at 75. ("Based on a review of current guidelines and standards of ecological risk assessment (EPA's 1998 Risk Assessment guidelines), the three assessment endpoints included in the PSE&G Application are necessary, but clearly are not sufficient for an adequate assessment of Adverse Impact.") (emphasis added)
[137] Campbell to Muszynski, January 19, 2001, at 2.
[138] 33 U.S.C. § 1326(b) (emphasis added).
[139] Decision of the Gen. Counsel No. 41, supra. See also, preamble to § 316(b) Regulations, 41 Fed. Reg. 17,387-88 (1976) (proposed Apr. 26, 1976) (subsequently withdrawn following invalidation of the accompanying Development Document by the Fourth Circuit in Appalachian Power v. Train, 566 F.2d 451 (4th Cir. 1977)); accord Seabrook II, 10 Env't Rep. Cas. (BNA) 1257 (EPA June 17, 1977).
[140] American Heritage Dictionary, 1150 (3d ed. 1992).
[141]
See, e.g., In the Matter of Boston Edison Electric Company (Pilgrim
Nuclear Station NPDES Permit Nos. MA00003557
and MA0025135).
[142] Id. (emphasis added).
[143] 2000 Salem Fact Sheet at 75.
[144] ESSA Report at 33.
[145] Id. at 10.
[146] Background Paper No. 3, supra.
[147] Id. at 2, 9.
[148] Id. at 9.
[149] ESSA Report at 33.
[150] Id. at 25.
[151] 2000 Salem Fact Sheet at 34.
[152] Brunswick I, at 2-3 (Initial Decision re: Permit No. NC007064).
[153] Brunswick Memorandum, supra (emphasis in original).
[154] Id.
[155] See, e.g., Hudson Riverkeeper Fund, 835 F. Supp. at 166.
[156] See 41 Fed. Reg. 17,387, 17,388 (1976).
[157]
See, EPA Region III January 19,
2001 comments to NJDEP draft NJPDES permit for PSE&G's SNGS.
Emphasis added.
[158] See United States Department of the Interior Fish and Wildlife Services January 10, 2001, comments to NJDEP draft NJPDES permit for PSE&G's SNGS at 4.
[159] ESSA Report at 45. (Although ESSA states “cooling towers, of course would minimize entrainment/impingement events” ESSA goes on to state that “there are engineering issues with this technology at Salem.”)
[160] 1989 Versar Report at VI-1. See also The Quick & The Dead at 446 for a discussion of the 1989 Versar Report findings.
[161] Carpenter Environmental Associates, Inc., Comments on Draft NJPDES Permit Issued to Public Service Electric & Gas Company Salem Generating Station (February 15, 2001) at 13 [herinafter Carpenter].
[162] Athens at *26, FN 9.
[163] 1989 Versar Report at VII-8.
[164] Athens at *26.
[165] Id.
[166] EPA, Economic and Engineering Analysis of the Proposed Section 326(b) New Facility Rule, August 2000.
[167] NRDC Comments at 21.
[168] Tellus Institute, Comments on the EPA's Proposed Regulations on Cooling Water Intake Structures for New Facilities at 9 (November 8, 2000) [hereinafter Tellus Comments].
[169]
Id.
[170] Id.
[171]
Id.
[172] Id. at 12.
[173] Athens at 26. (A once-through cooling system, similar to the system at Salem that withdraws 400 mgd was never considered for Athens because it clearly does not minimize the environmental impact and is therefore not BTA).
[174] Carpenter at 13.
[175] 1999 PSE&G Memo. PSE&G claims that the complexity and high cost are due to: (1) the permanence of existing site features; (2) scheduling and completing construction work that must accommodate the Station's operations requirements and regulatory restrictions; (3) the fundamental differences between the existing once-through system and a closed, cycle system; and (4) the difficulty of installing new, underground piping without encountering or disturbing buried obstructions.
[176] Id. at 158.
[177]Id.
[178] Carpenter at 9. (The technologies considered BTA for Salem by NJDEP include sound deterrents, light attraction technologies, and strobe light air bubbles.)
[179] Pisces Conservation Ltd., Technical Evaluation of US Environmental Protection Agency Proposed Cooling Water Intake Regulations for New Facilities at 28 (November 2000) [hereinafter Pisces Comments].
[180]
Id.
[181]
Id.
[182] 2000 Salem Fact Sheet at 80.
[183] 2000 Salem Fact Sheet at 34.
[184] Id.
[185] Id. at 34. (“As indicated by the Discharge Monitoring Report (DMR) data summary included for FAC C in the Permit Summary Tables in Section IX, PSE&G is in compliance with the intake flow limit. Considering the average of DMR data from 1/99 through 6/00 the average intake flow amount is 2698 million gallons per day.”)
[186] See, e.g., Background Paper No. 3, supra; 1976 Development Document, supra.
[187] 1976 Development Document, supra.
[188] Id
[189] Id.
[190] Id.
[191] Id. at 180.
[192] See, e.g., Brunswick I, (Initial Decision re: Permit No. NC007064). After discussing the lengthy approach channel used by Brunswick's intake system, the RA in Brunswick I determined that the design of the Brunswick intake structure did not fulfill the BTA requirements of Section 316(b) for minimizing adverse environmental impacts. Id. at 55-57. In Seabrook II, the EPA equated intake velocity with design. See Seabrook II, 10 Env't Rep. Cas. (BNA) at 1270. "[D]esigning for a single velocity cannot protect all fish at all times." Id
[193] Background Paper No. 3, supra.
[194] Id.
[195] Known as "conventional traveling screens, single-entry, single-exit vertical traveling screens are used by 60% of all steam-electric powerplants in the United States." Id. at 6. Conventional traveling screens were not designed with Section 316(b) in mind, these systems impinge fish, debris and refuse in screen-wells. Id. Powerplants using this type of technology have virtually unfettered adverse environmental impact.
[196] Some designs modify conventional systems in an attempt to reduce impingement losses by treating impinged organisms less harshly than impinged debris. Modified traveling screens attempt to sequester impinged organisms from debris with a series of high and low pressure sprays and thereafter return them to waterbodies with as little additional stress as possible. Id. The success of such intervention is often unclear. Id. at 6. One type of modified traveling screen, called a "Fletcher-Modified Ristroph screen, is currently being tested at a powerplant in the Delaware Estuary."
[197] Dual flow screens use a double-entry, single-exit vertical traveling screen design.
[198] The "Passavant screen uses a single-entry, double-exit design to increase screen surface area and thereby increase debris removal rates. Passavant screens do not reduce impingement losses any more than conventional vertical traveling screens." Id.
[199] Dual flow screens use a double-entry, single-exit vertical traveling screen design. These systems use an approach flow parallel to the intake screen which allows for increased debris removal capabilities. Dual flow screens do not reduce impingement losses any more than conventional vertical traveling screens. Id.
[200] Horizontal traveling screens rotate in a continuous fashion with an upstream face placed at an angle which guides fish away from the intake structure. Id. However, various mechanical problems have foreclosed extensive research into this type of technology although it may hold some promise in limited circumstances.
[201] Fine mesh screens mounted on traveling screens are virtually the only type of traveling screen designed to reduce both impingement and entrainment losses. Id. at 8. This type of system is still unproven and is not used continuously by any powerplant.
[202] Horizontal drum screens remove debris from intake water more efficiently than do conventional screens. Id. Horizontal drum screens are used extensively outside of the United States. These systems have not been shown to minimize fish losses more than conventional systems. Id
[203] Vertical drum screens, like horizontal drum screens are used outside the U.S. Id. They have been used for fish diversion and for protection of salmonids with varying success, but have yet to be prototype-tested by utilities in the United States. Id.
[204] Rotating disk screens rotate around a horizontal axis where high pressure sprays remove fish and debris before they enter the intake structure. Id. It is believed that horizontal rotation disk screens do not reduce impingement losses more than conventional systems. Id.
[205] Fixed screen technology is used at smaller stream powerplants in the United States. Id. at 9. Fixed screens require an operator to remove fish and debris from the fixed screen on a periodic basis. Id. Long impingement times and operator dependency make fixed screens a less desirable type of screen system
[206] Background Paper No. 3, supra.
[207] Wedgewire screens use a combination of exclusion and hydrodynamics to reduce significantly entrainment losses. Id. at 10. First, the screen's mesh size is smaller than the organisms susceptible to entrainment; therefore, fish, fry, larvae and eggs never make it into the intake structure. Id. Second, maintenance of a low, "through-slot velocity further impedes entrainment losses by forcing aquatic organisms away from the system." Id. Although shown to be effective at various powerplants in the United States, the potential of wedgewire screen technology has yet to be fully explored.
[208] Perforated pipes withdraw water through slots in cylindrical intake structures. Id. at 10. These devices, however, have thus far found limited use solely with powerplants having small intake flow requirements.
[209] Radial wells consist of a vertical pump caisson sunk below the water table. Id. Then perforated collector screen pipes (radial wells) are "jacked out through well ports in a surrounding porous aquifer." Id. Although radial wells reduce impingement and entrainment losses significantly, the need for a viable porous aquifer has limited their application. Id
[210] Porous dikes resemble a "breakwater engulfing an intake structure." Id. at 10. The core of the porous dike consists of cobble, stone, or gravel which acts as a physical and behavioral barrier to aquatic organisms. Id. Although porous dikes have been shown to reduce fish losses, they still represent a developing technology and have thus far been relegated to powerplants with small flow requirements. Id. at 11.
[211] Much like porous dikes, artificial filter beds surround intake structures and provide both a physical and behavioral barrier to aquatic organisms. Id. at 11. Artificial beds can be made with granular filter materials, id., or fabrics designed to prevent the entrance of debris and aquatic life into an intake structure. A prototype of an artificial bed with a fabric filter, called a "Gunder boom, is currently being tested at a powerplant along the Hudson River." See discussion of Hudson Riverkeeper, supra.
[212] Background Paper No. 3, supra.
[213] Louvers consist of a series of vertical panels placed at 90 degree angles to water flow direction. Id. at 12. Panel placement capitalizes on the natural tendency of fish to avoid changes in water flow direction and velocity. Id. Water currents parallel to the louvers then carry fish to a bypass system, id., and thereafter, to safety. The potential of louvers to reduce fish losses at powerplants has not been fully explored.
[214] Velocity caps are used on vertical intakes to convert vertical into horizontal flow, id., thereby taking advantage of the natural tendency of fish to avoid rapid changes in flow direction. Velocity caps have proven to be successful at many powerplants throughout the United States. Id. at 13. The potential of velocity caps to reduce fish losses at powerplants has not been fully explored.
[215] Fish barrier nets are large nets placed in front of intake structures. They perform both screening and behavioral purposes. Id. Fish barrier nets have proven to be useful on a seasonal basis at numerous powerplants, id., whose intake structures are located along significant fish migration paths.
[216] Air bubble, electrical, light, sound, cable and chain and water jet barriers are behavioral mechanisms using various electrical or physical means for deterring fish from entering an intake structure. Id. at 13-14. Electric barriers produce an electric shock promoting fish avoidance; light barriers and sound barriers produce light or sounds that deter fish; cable and chain barriers move through the water and have the effect of deterring fish from the area; and water jets produce a high pressure shield of water to usher fish away from the intake area. These technologies have each met with varying degrees of acceptance and interest. Id. at 14. For instance, a utility recently embarked on a study of sound barriers at a powerplant in the Delaware Estuary.
[217] Background Paper No. 3, supra.
[218] 2000 Salem Fact Sheet at 34.
[219] Id.
[220] Id. at 34. (“As indicated by the Discharge Monitoring Report (DMR) data summary included for FAC C in the Permit Summary Tables in Section IX, PSE&G is in compliance with the intake flow limit. Considering the average of DMR data from 1/99 through 6/00 the average intake flow amount is 2698 million gallons per day.”)
[221] Decision of the Gen. Counsel No. 41, supra. See also 1976 Development Document, supra; Brunswick I, at 58-60 (Initial Decision re: Permit No. NC007064); 41 Fed. Reg. 17,387, 17,390 (1976).
[222] Brunswick I, at 58-59 (Initial Decision re: Permit No. NC007064).
[223] See, e.g., id. at 59-60 (A reduction of cooling water intake volume should reduce the number of organisms subject to entrainment in direct proportion to the fractional flow reduction; "[C]ontinuous operation of its proposed . . . closed-cycle cooling system would result in a flow reduction at Brunswick of approximately 96%. This flow reduction should thus produce a 96% reduction in the number of organisms entrained by the plant. . . ." (footnote omitted). Similarly, Versar found that a 95% reduction in cooling water intake at Salem would result in a corresponding 95% reduction in fish impingement and entrainment. 1989 Versar Report, supra.
[224] Decision of the Gen. Counsel No. 41, supra (citing The Random House Dictionary of the English Language (unabridged 1970)).
[225] Id. at 179 (emphasis in original) (citation omitted).
[226] Decision of the Gen. Counsel No. 41, supra.
[227] The General Counsel's office cited with approval a summary of a conference debate on the Clean Water Act which occurred on October 4, 1972, which stated: "In response to concerns voiced by Senator Buckley that the Act would prevent the effective regulation of this problem [that is, the dangers posed to aquatic life by intake structures], Senator Muskie, the Chairman to the Senate Conference Committee, stated that EPA had authority under the [Clean Water] Act to regulate the withdrawal of cooling water so as to minimize adverse environmental aspects." Id. at 178-79.
[228] Decision of the Gen. Counsel No. 63, supra. The EPA Office of General Counsel found that "in certain cases, the only means of minimizing serious entrainment damage is to restrict the volume of water withdrawn." Id.
[229] Brunswick I, at 59 (Initial Decision re: Permit No. NC007064) (citations omitted).
[230] Id. at 60 n.158.
[231] Brunswick I, at 90 (Initial Decision re: Permit No. NC007064).
[232] Brunswick Press Release, supra.
[233] Brunswick I, at 90 (Initial Decision re: Permit No. NC007064).
[234] Brunswick Press Release, supra.
[235] Region IV, EPA, Record of Decision, Tampa Electric Co. Big Bend Unit 4: NPDES Permit No. FL0037044 (June 12, 1989) [hereinafter Big Bend ].
[236] Id.
[237] Id.
[238] Id.
[239] Id.
[240] See generally 1980 Hudson River Settlement Agreement, supra.
[241] Id.
[242] Seabrook II, 10 Env't Rep. Cas. (BNA) at 1270.
[243] Id.
[244] Decision of the Gen. Counsel No. 41, supra note 225, at 177; Decision of the Gen. Counsel No. 63, supra; Seabrook II, 10 Env't Rep. Cas. (BNA) at 1262 (stating that there is "no justification for giving `capacity' [this] restrictive meaning.").
[245] Decision of the Gen. Counsel No. 41, supra.
[246] Id. at 179.
[247] Decision of the Gen. Counsel No. 41, supra, at 181; Seabrook II, 10 Env't Rep. Cas. (BNA) 1257.
[248] Brunswick II, at 12 (Initial Decision re: Permit No. NC007064).
[249] Id. at 33.
[250] Id. at 60.
[251] Id. After this decision was challenged before the EPA Administrator, it was remanded to the RA. Upon remand the RA supplemented, but did not alter, its original decision. The case was ultimately settled. Brunswick Press Release, supra. While the settlement did not require a 96% reduction in intake flow, it did require a significant flow reduction in conjunction with a new screening device. Id.
[252] In re Application for a SPDES permit by Athens Generating Company, LP, 2000 N.Y. Env. Lexis 49, at *24 (June 2, 2000) [hereinafter Athens]. (A once-through cooling system, similar to the system at Salem that withdraws 400 mgd was never considered for Athens because it clearly does not minimize the environmental impact and is therefore not BTA)..
[253] Id. at *26.
[254]
Id.
(In Athens, a once-through
cooling system, similar to the system installed at Salem, was never
considered because it is clearly not BTA.
"Once through cooling, which withdraws 400 million gallons per
day with an average flow 277,778 gallons per minute was never considered
viable in this application.") Id.
[255] Id. at *33.
[256] Id. at *24.
[257] Pisces Comments at 27.
[258] Id. at 28.
[259] Id.
[260] 1976 Development Document, supra.
[261] Brunswick Memorandum, supra.
[262] Background Paper No. 3, supra.
[263] Id.
[264] Id.
[265] 1976 Development Document, supra.
[266] Id. at 178
[267] Id.
[268] Seabrook II, 10 Env't Rep. as. (BNA) at 1259.
[269] Seabrook IV, 1978 NPDES LEXIS 15, at *86 (emphasis added).
[270] Id.
[271] Id. at *47
[272] Id.
[273] Id. at *54
[274]
See Brunswick I, at 45 (Initial
Decision re: Permit No.
NC007064) (citing 1976 Development
Document). The RA in Seabrook I also quoted the 1976 Development Document in support of
his BTA decision to require installation of closed-cycle cooling towers:
Care
in the location of the intake [structure] can significantly minimize adverse
environmental impacts. . . . [A]mong
the many factors that can be considered in locating the intake structure to
minimize adverse environmental impacts [are] . . . : Avoidance of important spawning areas, fish migration paths,
shellfish beds or any location where field investigations have revealed a
particular concentration of aquatic life.
Seabrook II, 10 Env't Rep. Cas. (BNA) 1257, at 1264.
[275]
The Brunswick Memorandum, drafted in 1980 by the Office of Regional Counsel
for EPA Region IV, discussed Section 316(b) and the Brunswick Steam Plant.
Again, EPA noted that location of intake structures should avoid
estuarine environments. The Brunswick Memo firmly stated that intake structures
should be located in "areas where densities of immature stages of
finfish and shellfish are minimal."
Brunswick Memorandum, supra
note 275, at 2. The memorandum
then proceeded to point out that because "[e]stuarine nursery areas,
such as marshes and tidal creeks, are areas supporting maximum
densities of immature finfish and shellfish[,] intakes in such areas maximize
losses." Id. (emphasis in
original). The natural
conclusion drawn from these statements is that intake structures should not
be located in estuarine environments. It
is noteworthy that the memo refers to the 1976 Development Document, which
it characterizes as containing EPA's policy regarding Section 316(b), and
quotes the 1976 Development Document for the proposition "that intakes
located in estuarine nursery areas and/or on migratory pathways cannot meet
the 316[b] test." Id
[276] See generally 1980 Hudson River Settlement Agreement, supra.
[277] Id.
[278] Big Bend Permit No. FL0000817, supra.