Hope Creek Uprate

 

[Federal Register: March 11, 2008 (Volume 73, Number 48)]

[Notices]              

[Page 13032-13044]

From the Federal Register Online via GPO Access [wais.access. gpo.gov]

[DOCID:fr11mr08- 106]                        

 

------------ --------- --------- --------- --------- --------- --------- -----

 

NUCLEAR REGULATORY COMMISSION

 

[Docket No. 50-354]

 

 

PSEG Nuclear, LLC; Hope Creek Generating Station Final

Environmental Assessment and Finding of No Significant Impact; Related

to the Proposed License Amendment To Increase the Maximum Reactor Power

Level

 

AGENCY: U.S. Nuclear Regulatory Commission (NRC).

SUMMARY: As required by Title 10 of the Code of Federal Regulations (10

CFR) Part 51, the NRC has prepared a final Environmental Assessment

(EA) as its evaluation of a request by the PSEG Nuclear, LLC (PSEG) for

a license amendment to increase the maximum thermal power at Hope Creek

Generating Station (HCGS) from 3,339 megawatts-thermal (MWt) to 3,840

MWt. The EA assesses environmental impacts up to a maximum thermal

power level of 3,952 MWt, as the applicant's environmental report was

based on that power level. The NRC staff did not identify any

significant impact from the information provided in the licensee's EPU

application for HCGS or from the NRC staff's independent review. The

final EA and Finding of No Significant Impact are being published in

the Federal Register.

    The NRC published a draft EA and finding of no significant impact

on the proposed action for public comment in the Federal Register on

October 22, 2007 (72 FR 59563). Two sets of comments were received on

the draft EA: (1) From PSEG Nuclear, LLC by letter dated November 21,

2007 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML073600851) ; and (2) from the State of New Jersey

Department of Environmental Protection (NJDEP) by letter dated November

21, 2007 (ADAMS Accession No. ML073600859) . These comments are

addressed below.

 

Disposition of Public Comments on the Draft Environmental Assessment E

 

    PSEG Comment Number 1: Modify the Cooling Tower Impacts section to

more clearly reflect that NJDEP has issued the Title V Air Operating

Permit authorizing emissions at 42 lbs/hr upon approval of the [United

States Environmental Protection Agency] USEPA.

     NRC Response Number 1: This comment is a clarification and

editorial correction to the draft Environmental Assessment. Based on

this comment, the NRC staff revised the appropriate section of the

final EA.

     PSEG Comment Number 2: Modify the Discharge Impacts section to

reflect that the [total dissolved solids] TDS limits are indirectly in

the Title V Air Operating Permit and not in the [New Jersey Pollutant

Discharge Elimination System] NJPDES Permit.

     NRC Response Number 2: This comment is a clarification and

editorial correction to the draft Environmental Assessment. Based on

this comment, the NRC staff revised the appropriate section of the

final EA.

     PSEG Comment Number 3: Modify the Discharge Impacts section to

reflect that total suspended solids and [total organic carbon] TOC are

not routinely monitored and acute and chronic biological toxicity tests

are performed during each NJPDES Permit renewal.

     NRC Response Number 3: This comment is a clarification and

editorial correction to the draft Environmental Assessment. Based on

this comment, the NRC staff revised the appropriate section of the

final EA.

     PSEG Comment Number 4: Modify the Impacts on Aquatic Biota

section, Table 1, to reflect that Atlantic Croaker are considered to be

a single Atlantic coast stock.

     NRC Response Number 4: Upon further review, the NRC agrees with

the comment. Based on this comment, the NRC staff revised the

appropriate section of the final EA.

     PSEG Comment Number 5: Modify the Impacts on Aquatic Biota section

to identify inland silversides instead of tidewater silversides.

     NRC Response Number 5: Upon further review, the NRC agrees with

the comment. Based on this comment, the NRC staff revised the

appropriate section of the final EA.

     PSEG Comment Number 6: Modify the Impacts on Aquatic Biota section

to reflect the extensive biological monitoring program at the adjacent

Salem Generating Station, reflect the

 

[[Page 13033]]

 

potential escape mechanism at the intake based on the low intake

velocity, and change ``no environmental monitoring'' to ``no intake

aquatic monitoring.' ' There are extensive environmental monitoring

programs in place at HCGS.

     NRC Response Number 6: Based on this comment, the NRC staff

revised the appropriate section of the final EA.

     PSEG Comment Number 7: Modify the Radioactive Waste Stream Impacts

section to remove the redundant use of the word ``waste.''

     NRC Response Number 7: This comment is an editorial correction to

the draft Environmental Assessment. Based on this comment, the NRC

staff revised the appropriate section of the final EA.

     PSEG Comment Number 8: Modify the Gaseous Radioactive Waste and

Offsite Doses section to reflect values in Table 5-3 of PSEG's

Environmental Report for EPU.

     NRC Response Number 8: This comment is a clarification correction

to the draft Environmental Assessment. Based on this comment, the NRC

staff revised the appropriate section of the final EA.

     PSEG Comment Number 9: Modify the Offsite Radiation Doses section

to reflect the information contained in Section 5.2.1 of PSEG's

Environmental Report for EPU.

     NRC Response Number 9: This comment is a clarification correction

to the draft EA. Based on this comment, the NRC staff revised the

appropriate section of the final EA.

     PSEG Comment Number 10: Modify the Summary section, Table 3, to

reflect only those values that were discussed in the main text.

     NRC Response Number 10: This comment is an editorial correction to

the draft EA. Based on this comment, the NRC staff revised the

appropriate section of the final EA.

     NJDEP Comment Number 1: The proposed modification is subject to

the Federal Consistency provisions of the Federal Coastal Zone

Management Act (CZMA), and as such, a Federal Consistency determination

is required. On July 3, 2007, the NJDEP's Division of Land Use

Regulation issued the Federal Consistency certification for the

proposed power project.

     NRC Response Number 1: This comment is a clarification correction

to the draft Environmental Assessment. Based on this comment, the NRC

staff revised the appropriate section of the final EA.

     NJDEP Comment Number 2: The proposed increase in power output

would result in a small increase to the temperature of the water being

discharged into the Delaware River. Although the discharge is within

the limits allowed by the current permit, the [NJDEP's Division of Fish

and Wildlife] DFW has concerns over potential impacts to resident and

migratory fish species within the area.

     NRC Response Number 2: Blowdown temperature and composition, and

Delaware Estuary water temperatures would remain in compliance with the

station's NJPDES permit, and the proposed EPU would not result in

changes in any other effluents to the estuary. Therefore, the NRC staff

concludes that the proposed EPU would result in negligible impacts on

the Delaware Estuary from HCGS discharge. Based on this comment, the

NRC staff did not revise the final EA.

     NJDEP Comment Number 3: Potential impacts identified by the Draft

EA acknowledged that increased evaporation would leave behind more

solids in the blowdown, so the concentration of total dissolved solids

(TDS) in the effluent would be an average of about 9 percent higher

than under current operations. While this is in compliance with the

station's NJPDES permit, the Division has concerns over potential

impacts to resident and migratory fish species and shellfish within the

area.

     NRC Response Number 3: Blowdown temperature and composition, and

Delaware Estuary water temperatures would remain in compliance with the

station's NJPDES permit, and the proposed EPU would not result in

changes in any other effluents to the estuary. Therefore, the NRC staff

concludes that the proposed EPU would result in negligible impacts on

the Delaware Estuary from HCGS discharge. Based on this comment, the

NRC staff did not revise the final EA.

     NJDEP Comment Number 4: The potential impacts to aquatic biota

from the proposed action are primarily due to operation of the cooling

water system withdraws. Although no volume and/or velocity changes to

the circulating water or service water systems are expected due to the

proposed EPU, the DFW continues to be concerned for the destruction of

fish and/or shellfish species via intake and discharge of water at this

plant. While the identity of species potentially affected by

entrainment, impingement, and heat shock may be inferred from

ecological information about the Delaware Estuary, the species affected

cannot be verified, and the numbers cannot be quantified because no

environmental monitoring programs are conducted at the facility. It is

expected that a percentage of impinged organisms may likely die,

partially due to the fish-return system not functioning continuously to

minimize mortality at present. It is expected all organisms entrained

at HCGS are probably killed from exposure to heat, mechanical,

pressure-related stresses, and/or biocidal treatment before being

discharged to the estuary. Although the proposed action would not

change the volume or rate of cooling water withdrawn, the DFW has

concerns regarding the number of individual fish and shellfish, larvae

and eggs destroyed by the plant and any associated temperature rise in

the Delaware Estuary. The entrainment kill should be verified to

species and quantified in the future to address these concerns. It is

anticipated that any new processes that are developed for the other

Salem units to increase impingement survivability and decrease

entrainment will be employed by this plant as well automatically.

     NRC Response Number 4: Under the proposed EPU, water withdrawal

rates would not change from present conditions. Entrainment and

impingement impacts may change over time due to changes in the aquatic

populations even though HCGS's water withdrawal rate would not change

from present conditions. Impacts due to impingement and entrainment

losses are minimized because the closed-cycle cooling system at the

plant minimizes the amount of cooling water withdrawn from and heated

effluent returned to the estuary. The water quality of the effluent

(e.g., temperature, toxicity, TDS concentrations) would continue to

meet present NJPDES permit conditions for protection of aquatic life.

The staff concludes that the proposed EPU would have no significant

impact to aquatic biota. Impingment and entrainment effects are

regulated by NJDEP under Clean Water Act 316(b), and heat shock is

regulated by NJDEP under 316(a) as part of NJPDES permitting. NJPDES

permit levels are not part of NRC jurisdiction. Based on this comment,

the NRC staff did not revise the final EA.

     NJDEP Comment Number 5: National Marine Fisheries Service (NMFS)

issued a letter dated January 26, 2007, that provided information on

the endangered shortnose sturgeon; Atlantic sturgeon, a candidate

species for listing; and five species of endangered or threatened sea

turtles: Loggerhead, Kemp's ridley, leatherback, green, and hawksbill

turtles. The Nuclear Regulatory Commission (NRC) staff investigated the

effects of the HCGS operation on these species and found that the

primary concern for these endangered and threatened species is the risk

of

 

[[Page 13034]]

 

impingement or entrainment due to cooling water intake by the plant.

The HCGS has reported no takes of any of the endangered or threatened

species listed above. Although the proposed EPU would not change the

intake flow, and, therefore, would not increase impingement and

entrainment of these species, the DFW remains concerned regarding

potential takes of endangered species.

     NRC Response Number 5: Under the proposed EPU, water withdrawal

rates would not change from present conditions. Entrainment and

impingement impacts may change over time due to changes in the aquatic

populations even though HCGS's water withdrawal rate would not change

from present conditions. Impacts due to impingement and entrainment

losses are minimized because the closed-cycle cooling system at the

plant minimizes the amount of cooling water withdrawn from and heated

effluent returned to the estuary. The water quality of the effluent

(e.g., temperature, toxicity, TDS concentrations) would continue to

meet present NJPDES permit conditions for protection of aquatic life.

The staff concludes that the proposed EPU would have no significant

impact to aquatic biota. Impingment and entrainment effects are

regulated by NJDEP under Clean Water Act 316(b), and heat shock is

regulated by NJDEP under 316(a) as part of NJPDES permitting. NJPDES

permit levels are not part of NRC jurisdiction. Based on this comment,

the NRC staff did not revise the final EA.

     NJDEP Comment Number 6: The EA notes that an Essential Fish

Habitat (EFH) for the proposed EPU was sent to the National Marine

Fisheries Service (NMFS) under separate cover to initiate an EFH

consultation. We recommend that the NRC should issue no final decision

on this proposal until NMFS consultations are concluded.

     NRC Response Number 6: The staff agrees with this comment. By

letter dated July 13, 2007 (ADAMS Accession No. ML072000450) , NMFS

found the EFH assessment satisfactory. Based on this comment, the NRC

staff revised the appropriate section of the final EA.

     NJDEP Comment Number 7: No impacts are expected to avian species.

     NRC Response Number 7: The staff agrees with this comment;

however, no changes to the final EA are warranted.

     NJDEP Comment Number 8: According to the EA, no changes to the

Hope Creek Generating Station circulating water or service water

systems are expected due to the proposed EPU; therefore, the proposed

EPU would not increase the amount of water withdrawn from or discharged

to the Delaware Estuary. As a result, the intake issue appears to be

unaffected by the power re-rating.

     NRC Response Number 8: The staff agrees with this comment;

however, no changes to the final EA are warranted.

     NJDEP Comment Number 9: This Bureau has determined that because

the permittee is willing to comply with its current discharge limits,

the regulation of the discharge via NJPDES appears to be unaffected by

the power re-rating. In the current NJPDES permit, there is no effluent

flow limit and there is no total dissolved solids (TDS) requirement

since the facility discharges to saline waters. This is due to the fact

that there are currently no New Jersey Surface Water Quality Standards

for TDS. Through the administering of the NJPDES program, this Bureau

will continue to require effluent characterization of the cooling tower

blowdown to monitor any changes to the toxic pollutants that may or may

not occur due to the proposed EPU.

     NRC Response Number 9: The staff agrees with this comment;

however, no changes to the final EA are warranted.

     NJDEP Comment Number 10: The information contained in the EA

indicates that the power output of the reactor will increase

approximately 15-percent. It can be concluded that this power increase

will raise magnetic field emissions from the lines and therefore,

elevate magnetic fields along the right-of-way. These changes will

increase the magnetic field exposure of the population living closer

than 400 feet from the center of the transmission line configuration.

At this point in time, the consensus among the scientific community is

that there is inconclusive evidence to suggest that long-term exposure

to magnetic fields from power lines would result in adverse health

outcomes. However, for new or modified lines, many health-based

organizations are still recommending reducing magnetic fields if low or

no-cost options exist. In a June 2007 fact sheet put forth from the

World Health Organization (WHO Fact sheet No. 322), the following

guidance is issued: ``When constructing new facilities and designing

new equipment low-cost ways of reducing exposures may be explored.''

Therefore, in light of such uncertainty, if there are any changes that

will be made to the power delivery system that would lower the magnetic

fields from the power lines, it may be prudent to explore such options.

     NRC Response Number 10: The proposed EPU does not require the

modification or building of new transmission lines. Therefore, the

guidance in WHO Fact Sheet No. 322 is not applicable. There is no

scientific consensus regarding the health effects of electromagnetic

fields (EMFs) produced by operating transmission lines. Therefore, the

licensee did not quantify the chronic effects of EMF on human and

biota. The potential for chronic effects for these fields continues to

be studied and is not known at this time. The National Institute of

Environmental Health Sciences (NIEHS) directs related research through

the U.S Department of Energy (DOE). A 2003 NIEHS study published in

Environmental Health Perspectives, Volume 111, Number 3, March 2003,

titled ``Power-Line Frequency Electromagnetic Fields Do Not Induce

Changes in Phosphorylation, Localization, or Expression of the 27-

Kilodalton Heat Shock Protein in Human Keratinocytes' ' by Biao Shi,

Behnom Farboud, Richard Nuccitelli, and R. Rivkah Isseroff of the

University of California-- Davis contains the following conclusion:

 

    ''The linkage of the exposure to the power-line frequency (50-60

Hz) electromagnetic fields (EMF) with human cancers remains

controversial after more than 10 years of study. The in vitro

studies on the adverse effects of EMF on human cells have not

yielded a clear conclusion. In this study, we investigated whether

power-line frequency EMF could act as an environmental insult to

invoke stress responses in human keratinocytes using the 27-kDa heat

shock protein (HSP27) as a stress marker. After exposure to 1 gauss

(100 [mu]T) EMF from 20 min to 24 hr, the isoform pattern of HSP27

in keratinocytes remained unchanged, suggesting that EMF did not

induce the phosphorylation of this stress protein. EMF exposure also

failed to induce the translocation of HSP27 from the cytoplasm to

the nucleus. Moreover, EMF exposure did not increase the abundance

of HSP27 in keratinocytes. In addition, we found no evidence that

EMF exposure enhanced the level of the 70-kDa heat shock protein

(HSP70) in breast or leukemia cells as reported previously.

Therefore, in this study we did not detect any of a number of stress

responses in human keratinocytes exposed to power-line frequency

EMF.''

 

    To date, there is not sufficient data to cause the NRC staff to

change its position with respect to the chronic effects of

electromagnetic fields. If in the future, the NRC staff finds that,

contrary to current indications, a consensus has been reached by

appropriate Federal health agencies that there are adverse health

effects from electromagnetic fields, the NRC staff will recommend to

the Commission to change its current position regarding EMF. The NRC

staff did not revise the final EA based on this comment.

     NJDEP Comment Number 11: The NJDEP's Air Quality Permitting Office

approved the Title V air permit

 

[[Page 13035]]

 

modification for this project on August 7, 2007. This approval along

with a request for a single source state implementation plan (SIP) for

a variance to Subchapter 6 was sent to the Environmental Protection

Agency (EPA) on November 2, 2007. The Air Quality Permitting Office has

not yet received a response from the EPA.

     NRC Response Number 11: The staff agrees with this comment;

however, no changes to the final EA are warranted.

 

Environmental Assessment

 

Plant Site and Environs

 

    HCGS is located on the southern part of Artificial Island, on the

east bank of the Delaware River, in Lower Alloways Creek Township,

Salem County, New Jersey. While called Artificial Island, the site is

actually connected to the mainland of New Jersey by a strip of

tideland, formed by hydraulic fill from dredging operations on the

Delaware River by the U.S. Army Corps of Engineers. The site is 15

miles south of the Delaware Memorial Bridge, 18 miles south of

Wilmington, Delaware, 30 miles southwest of Philadelphia, Pennsylvania,

and 7.5 miles southwest of Salem, New Jersey. The station is located on

a 300-acre site.

    The site is located in the southern region of the Delaware River

Valley, which is defined as the area immediately adjacent to the

Delaware River and extending from Trenton to Cape May Point, New

Jersey, on the eastern side, and from Morrisville, Pennsylvania, to

Lewes, Delaware, on the western side. This region is characterized by

extensive tidal marshlands and low-lying meadowlands. Most land in this

area is undeveloped. A great deal of land adjacent to the Delaware

River, near the site, is public land, owned by the Federal and State

governments. The main access to the plant is from a road constructed by

PSEG. This road connects with Alloways Creek Neck Road, about 2.5

miles, east of the site. Access to the plant site and all activities

thereon are under the control of PSEG.

 

Identification of the Proposed Action

 

    HCGS is a single unit plant that employs a General Electric BWR

that was designed to operate at a rated core thermal power of 3,339

MWt, at 100-percent steam flow, with a turbine-generated rating of

approximately 1,139 megawatts-electric (MWe).

    In 1984, NRC issued operating license NPF-57 to HCGS, authorizing

operation up to a maximum power level of 3,293 MWt. In 2001, NRC

authorized a license amendment for a 1.4 percent power uprate from

3,293 MWt to 3,339 MWt and issued an Environmental Assessment and

Finding of No Significant Impact for Increase in Allowable Thermal

Power Level (NRC 2001).

    By letter dated September 18, 2006, PSEG proposed an amendment to

the operating license for HCGS, to increase the maximum thermal power

level by approximately 15 percent, from 3,339 MWt to 3,840 MWt. The

change is considered an EPU because it would raise the reactor core

power levels more than 7 percent above the originally licensed maximum

power level.

 

The Need for the Proposed Action

 

    PSEG (2005) evaluated the need for additional electrical generation

capacity in its service area for the planning period of 2002-2011.

Information provided by the North American Electric Reliability Council

showed that, in order to meet projected demands, generating capacity

must be increased by at least 2 percent per year for the Mid-Atlantic

Area Council and the PJM Interconnection, LLC (PSEG 2005). Such demand

increase would exceed PSEG's capacity to generate electricity for its

customers.

    PSEG determined that a combination of increased power generation

and purchase of power from the electrical grid would be needed to meet

the projected demands. Increasing the generating capacity at HCGS was

estimated to provide lower-cost power than can be purchased on the

current and projected energy market. In addition, increasing nuclear

generating capacity would lessen the need to depend on fossil fuel

alternatives that are subject to unpredictable cost fluctuations and

increasing environmental costs.

 

Environmental Impacts of the Proposed Action

 

    This EA summarizes the non-radiological and radiological impacts

that may result from the proposed action.

 

Non-Radiological Impacts

 

Land Use Impacts

 

    The potential impacts associated with land use (including

aesthetics and historic and archaeological resources) include impacts

from construction and plant modifications at HCGS. While some plant

components would be modified, most plant changes related to the

proposed EPU would occur within existing structures, buildings, and

fenced equipment yards housing major components within the developed

part of the site. No new construction would occur, and no expansion of

buildings, roads, parking lots, equipment storage areas, or

transmission facilities would be required to support the proposed EPU

(PSEG 2005).

    Existing parking lots, road access, offices, workshops, warehouses,

and restrooms would be used during construction and plant

modifications. Therefore, land use would not change at HCGS. In

addition, there would be no land use changes along transmission lines

(no new lines would be required for the proposed EPU), transmission

corridors, switchyards, or substations. Because land use conditions

would not change at HCGS and because any disturbance would occur within

previously disturbed areas, there would be no impact to aesthetic

resources and historic and archeological resources in the vicinity of

HCGS (PSEG 2005).

    The Coastal Zone Management Act (CZMA) was promulgated to encourage

and assist States and territories in developing management programs

that preserve, protect, develop, and, where possible, restore the

resources of the coastal zone. A ``coastal zone'' is generally

described as the coastal waters and the adjacent shore lands strongly

influenced by each other. This includes islands, transitional and

intertidal areas, salt marshes, wetlands, beaches, and Great Lakes

waters. Activities of Federal agencies that are reasonably likely to

affect coastal zones shall be consistent with the approved coastal

management program (CMP) of the State or territory to the maximum

extent practical. The CZMA provisions apply to all actions requiring

Federal approval (new plant licenses, license renewals, materials

licenses, and major amendments to existing licenses) that affect the

coastal zone in a State or territory with a Federally approved CMP. The

proposed EPU is subject to the Federal Consistency provisions of the

Federal Coastal Zone Management Act (CZMA), and as such, a Federal

Consistency determination is required. On April 23, 2007, PSEG

submitted an application requesting the State of New Jersey to perform

the Federal Consistency determination in accordance with CZMA. On July

3, 2007, the New Jersey Department of Environmental Protection (NJDEP)

Land Use Regulation Program, acting under Section 307 of the Federal

Coastal Management Act, issued the Federal Consistency certification

for the proposed EPU.

    The impacts of continued operation of HCGS under EPU conditions are

bounded by the evaluation in the FES for operation (NRC 1984).

Therefore, the potential impacts to land use, aesthetics,

 

[[Page 13036]]

 

and historic and archaeological resources from the proposed EPU would

not be significant.

 

Cooling Tower Impacts

 

    HCGS has one natural draft cooling tower that is currently used to

reduce the heat output to the environment. The potential impacts

associated with cooling tower operation under the proposed EPU could

affect aesthetics, salt drift deposition, noise, fogging or icing,

wildlife, and particulate emissions.

    The proposed EPU would not result in significant changes to

aesthetics such as cooling tower plume dimension at HCGS. Atmospheric

emissions from the natural draft cooling tower consist primarily of

waste heat and water vapor resulting in persistent cloudlike plumes.

The size of the cooling tower plume depends on the meteorological

conditions such as temperature, dew point, and relative humidity. For

the proposed EPU, NRC does not anticipate any change in the dimension

of the plume under equivalent meteorological conditions as evaluated in

the FES. Therefore, the NRC staff concludes that there would be no

significant aesthetic impacts associated with HCGS cooling tower

operation for the proposed action.

    Native, exotic, and agricultural plant productivity may be

adversely affected by the increased salt concentration in the drift

deposited directly on soils or directly on foliage. FES has indicated

that the salt drift deposition must be above 90 lbs/acre/year before

agriculture plant productivity would be reduced. PSEG has estimated

that the proposed EPU would not significantly increase the rate of salt

drift deposition from the increase in cooling tower operation. PSEG has

estimated that the increase in salt drift deposition rate would be 9

percent to a maximum of 0.109 lbs/acre/year. Therefore, the NRC staff

concludes that there would be no significant salt drift deposition

impacts associated with HCGS cooling tower operation for the proposed

action.

    Because the HCGS cooling tower is natural draft, no increase in

noise is expected. Therefore, the NRC staff concludes that there would

be no significant noise impacts associated with HCGS cooling tower

operation for the proposed action.

    PSEG has indicated that there would be no significant increase in

fogging or icing expected for the proposed EPU. Increased ground-level

fogging and icing resulting from water droplets in the cooling tower

drift may interfere with highway traffic. The 1984 FES evaluated the

impacts of fogging and icing associated with the operation of the

natural draft cooling tower at HCGS and found these impacts to be

insignificant and inconsequential. The fact that the nearest

agricultural or residential land is located several miles from the site

further minimizes the potential for impact. Therefore, the NRC staff

concludes that there would be no significant fogging or icing impacts

associated with HCGS cooling tower operation for the proposed action.

    The 1984 FES has stated that although some birds may collide with

cooling tower, unpublished surveys at existing cooling towers indicated

that the number would be relatively small. The proposed EPU would not

increase the risk of wildlife colliding with cooling tower. Therefore,

the NRC staff concludes that there would be no significant wildlife

impacts associated with HCGS cooling tower operation for the proposed

action.

    The proposed EPU would increase the particulates emission rate from

the HCGS cooling tower, from the current permitted rate of 29.4 pounds

per hour (lbs/hr) to a rate of 35.6 lbs/hr (maximum 42.0 lbs/hr).

Particulates (primarily salts) from the cooling tower have an

aerodynamic particle size of less than 10 microns in diameter (PM10).

The NJDEP has imposed a maximum hourly emission rate for particulates

at 30 lbs/hr. Therefore, the projected particulate emission rate from

the HCGS cooling tower, due to the proposed EPU, could exceed the NJDEP

emission regulatory limit. On March 30, 2007, NJDEP issued a Public

Notice and Draft Title V Air Operating Permit for the HCGS cooling

tower, proposing to authorize a variance to the HCGS air operating

permit with an hourly emission rate of 42 lbs/hr (NJDEP 2007a). On June

13, 2007, NJDEP issued the final Title V Air Operating Permit for HCGS

allowing a 42 lbs/hr particulate emission rate for the proposed EPU

upon approval of the State Implementation Plan by USEPA.

    Since particulates from HCGS cooling tower consist primarily of

salts with particle size of less than 10 microns, the FES evaluated the

environmental impacts on air quality and found the impacts to be minor.

Furthermore, a prevention of significant deterioration (PSD) non-

applicability analysis was submitted to the U.S. Environmental

Protection Agency (EPA) Region 2, by PSEG on March 4, 2004. Based on

the information provided by PSEG, EPA concluded that the EPU project

would not result in a significant increase in emissions and would not

be subject to PSD review (ML071240216) . In addition, NJDEP has stated

that the Bureau of Technical Services reviewed the Air Quality Modeling

for the proposed Hope Creek uprate project and determined that the

project would meet the National Ambient Air Quality Standards and the

New Jersey Ambient Air Quality Standards. Therefore, the NRC staff

concludes that there would be no significant particulate emission

impacts associated with HCGS cooling tower operation for the proposed

action.

 

Transmission Facility Impacts

 

    The potential impacts associated with transmission facilities

include changes in transmission line right-of-way (ROW) maintenance and

electric shock hazards due to increased current. The proposed EPU would

not require any physical modifications to the transmission lines.

    PSEG's transmission line ROW maintenance practices, including the

management of vegetation growth, would not change. PSEG did not provide

an estimate of the increase in the operating voltage due to the EPU.

Based on experience from EPUs at other plants, the NRC staff concludes

that the increase in the operating voltage would be negligible. Because

the voltage would not change significantly, there would be no

significant change in the potential for electric shock. Modifications

to onsite transmission equipment are necessary to support the EPU; such

changes include replacement of the high- and low-pressure turbines, and

the replacement of the main transformer (PSEG 2005). No long-term

environmental impacts from these replacements are anticipated.

    The proposed EPU would increase the current, which would affect the

electromagnetic field. The National Electric Safety Code (NESC)

provides design criteria that limit hazards from steady-state currents.

The NESC limits the short-circuit current to the ground to less than 5

milliamperes. The transmission lines meet the applicable shock

prevention provision of the NESC. Therefore, even with the slight

increase in current attributable to the EPU, adequate protection is

provided against hazards from electrical shock.

    There would be an increase in current passing through the

transmission lines associated with the increased power level of the

proposed EPU. The increased electrical current passing through the

transmission lines would cause an increase in electromagnetic field

strength. However, there is no scientific consensus regarding the

health effects of electromagnetic fields (EMFs) produced by operating

transmission lines. Therefore, the licensee did not quantify the

chronic effects of EMF on human and biota. The potential for chronic

effects for these fields continues to be studied and is not

 

[[Page 13037]]

 

known at this time. The National Institute of Environmental Health

Sciences (NIEHS) directs related research through the U.S. Department

of Energy (DOE). A 2003 NIEHS study published in Environmental Health

Perspectives, Volume 111, Number 3, March 2003, titled ``Power-Line

Frequency Electromagnetic Fields Do Not Induce Changes in

Phosphorylation, Localization, or Expression of the 27-Kilodalton Heat

Shock Protein in Human Keratinocytes' ' by Biao Shi, Behnom Farboud,

Richard Nuccitelli, and R. Rivkah Isseroff of the University of

California-- Davis contains the following conclusion:

 

    ``The linkage of the exposure to the power-line frequency (50-60

Hz) electromagnetic fields (EMF) with human cancers remains

controversial after more than 10 years of study. The in vitro

studies on the adverse effects of EMF on human cells have not

yielded a clear conclusion. In this study, we investigated whether

power-line frequency EMF could act as an environmental insult to

invoke stress responses in human keratinocytes using the 27-kDa heat

shock protein (HSP27) as a stress marker. After exposure to 1 gauss

(100 [mu]T) EMF from 20 min to 24 hr, the isoform pattern of HSP27

in keratinocytes remained unchanged, suggesting that EMF did not

induce the phosphorylation of this stress protein. EMF exposure also

failed to induce the translocation of HSP27 from the cytoplasm to

the nucleus. Moreover, EMF exposure did not increase the abundance

of HSP27 in keratinocytes. In addition, we found no evidence that

EMF exposure enhanced the level of the 70-kDa heat shock protein

(HSP70) in breast or leukemia cells as reported previously.

Therefore, in this study we did not detect any of a number of stress

responses in human keratinocytes exposed to power-line frequency

EMF.''

 

    To date, there is not sufficient data to cause the NRC staff to

change its position with respect to the chronic effects of

electromagnetic fields. If in the future, the NRC staff finds that,

contrary to current indications, a consensus has been reached by

appropriate Federal health agencies that there are adverse health

effects from electromagnetic fields, the NRC staff will recommend to

the Commission to change its current position regard EMF.

    The 1984 FES evaluated bird mortality resulting from collision with

towers and conductors. The FES has estimated that only 0.07 percent of

the mortality of waterfowls from causes other than hunting resulted

from collision with towers and conductors at HCGS. Because the proposed

EPU does not require physical modifications to the transmission line

system, the additional impacts of bird mortality would be minimal.

    The impacts associated with transmission facilities for the

proposed action would not change significantly relative to the impacts

from current plant operation. There would be no physical modifications

to the transmission lines, transmission line ROW maintenance practices

would not change, there would be no changes to transmission line ROW or

vertical ground clearances, and electric current passing through the

transmission lines would increase only slightly. Therefore, the NRC